8 – Reconstruction of villages

Objective of the program

To reconstruct, to recover and to relocate the locations of Novo Bento Rodrigues, Paracatu and Gesteira, with specific projects for each location, as well as a specific project for the reconstruction of the Gesteira school. After the completion of the reconstruction and resettlement, to monitor the resettlements part of the social programs of the locations for up to 36 months.

Progress of Program

Bento Rodrigues
- Completion of work on ID 36-UH2.

Bento Rodrigues
In August 2024, a transfer of R$121,071.80 was made to the municipality of Marilândia, referring to the request for Adaptation and preparation of projects for the sewage systems in the localities of São Marcos, Monte Sinai, Patrão Mor, Brejal, Alto Liberdade and the Municipal Headquarters;

In August 2024, a transfer of R$106,135.92 was made to the municipality of Mariana, referring to the request for Management of the work to implement the SES of Mariana/MG;

Gesteira
In August 2024, a transfer of R$187,083.94 was made to the municipality of Sem Peixe, referring to the request for work on the Implementation of sewage treatment in the District of São Bartolomeu and the amount of R$542,728.06 referring to the request for work on Complementation of counterpart resources for TC/PAC 0366/14;

In August 2024, a transfer of R$269,390.95 was made to the municipality of Caratinga, referring to the request for the expansion of the Caratinga sanitary landfill;

Completion of work on ID 215.

Novo Bento Rodrigues:
- Completion of work on ID 39.
- Completion of work on ID 125A.
- Completion of work on ID N.A7.
- Completion of work on ID 36_UH1.

Paracatu:
- Completion of work on ID 72B2.
- Completion of work on ID 72B1.
- Completion of work on ID 29A.
- Completion of work on ID 129A.
- Completion of work on ID 23A1.

Family:
- Completion of work on ID 20B.
- Completion of work on ID 41.
- Approval of payment ID 246.
- Approval of payment ID 126A1.
- Approval of payment ID NA37.
- Approval of payment ID 48UH1.
- Approval of payment ID 48UH2.
- Approval of payment ID 23UH2.
- Approval of payment ID ID17.

Novo Bento Rodrigues:
- Completed work: Completion of work on ID 164
- Completed work: Completion of work on ID 209

Paracatu:
- Completed work: Completion of work on the ID Football Field.

Novo Bento Rodrigues:
- Completion of work on ID 15A.
- Completion of work on ID 259.
- Completion of work on the ID Archaeological Site.

Paracatu:
- Completion of work on the ID Capela Santo Antônio.

Novo Bento Rodrigues:
- Completion of work on ID 53.
- Completion of work on ID 137A1-UH.
- Completion of work on ID 171.
- Completion of work on ID 251.
- Completion of work on ID 36-UH2.
- Completion of work on ID 75.
- Completion of work on ID Igreja das Mercês.
- Completion of work on the ID Casa Paroquial.

Family:
- ID NA Payment Approval.
- Approval of Payment ID 91B.

Novo Bento Rodrigues:
- Completion of work on ID 146B.
- Completion of work on ID São Bento.

Paracatu:
- Approval of Payment ID 44.

Family
- Completion of work on ID 110.

- Novo Bento Rodrigues
Completion of work on ID 15B.
Completion of work on ID 51.
Completion of work on ID 116.
Completion of work on ID 93A.
Completion of work on ID 36-UH3.
Monetary Payment - Payment Approval - ID INQ32.
Monetary Payment - Payment Approval - ID 134.
Completion of work on ID 96A.

- Paracatu
Completion of work on the Cemetery.
Completion of work on Casa São Vicente.

- Family
Completion of work on ID 23A.
Completion of work on ID 139.
Completion of work on NA4.
Completion of work on ID NN28.
Monetary Payment - Payment Approval - ID NN27.
Monetary Payment - Payment Approval - ID 82.
Monetary Payment - Payment Approval - ID NN37.
Monetary Payment - Payment Approval - NA.

Novo Bento Rodrigues
Completion of work on ID 98.
Monetary Payment - Payment Approval - ID 180B.
Completion of work on ID 96A2.

Family
Completion of work on ID 99A.

Novo Bento Rodrigues
Completion of work on ID 60.
Completion of work on ID 188.
Completion of work on ID 149.
Completion of work on ID 76B.
Completion of work on ID AHOBERO.
Monetary Payment - Payment Approval - ID 198A-UH1
Monetary payment - Payment Approval - ID 198B-UH1"
Monetary payment - Payment Approval - ID 198A-UH2"
Monetary payment - Payment Approval - ID 89A"
Monetary payment - Payment Approval - ID 198B-UH2"
Monetary payment - Payment Approval - ID 198D"
Monetary payment - Payment Approval - ID 198C"
Monetary payment - Payment Approval - ID 138"
Completion of work on ID 75.
Completion of work on ID 66.

Gesteira
There were no relevant facts this month.

Paracatu
Completion of work on the ID Archaeological Site.
Monetary Payment - Payment Approval - ID 24A

Family
Completion of work on ID 81.
Completion of work on ID 19.
Monetary Payment - Payment Approval - ID NA 30
Monetary payment - Payment Approval - ID NA 130

Bento Rodrigues
Completion of work on ID 142
Completion of work on ID 146A
Completion of work on ID CC.123
Completion of work on ID 36-UH4

Family
Monetary Payment - Payment Approval - ID 132A-UH1.
Monetary Payment - Approval of Payment - ID 132A.
Monetary Payment - Payment Approval - ID NN.50.
Monetary Payment - Approval of Payment - ID NN.70.
Monetary Payment - Payment Approval - ID 125B.

Paracatu
Monetary Payment - Payment Approval - ID 136.

Bento Rodrigues

Completion of works on ID22.
Completion of works on ID223.
Completion of Work on ID181-UH1.
Completion of Work on ID181-UH2.
Completion of the Renovation of batch ID175.
Monetary Payment - Payment Approval - ID243.
Monetary Payment - Payment Approval - ID99.
Monetary Payment - Payment Approval - ID255

Paracatu
Monetary Payment - Payment Approval - ID63.
Monetary Payment - Payment Approval - ID5.
Monetary Payment - Payment Approval - ID24.

Family

Monetary Payment ID NN.13.

Bento Rodrigues

Completion of works on IDCC137A1.
Completion of works on IDNN123A.

Gesteira

There were no Relevant Facts this month.

Paracatu de Baixo

There were no Relevant Facts this month.

Family

There were no Relevant Facts this month.

Bento Rodrigues

Completion of Work on ID217A.
Completion of the Renovation of batch ID137A2

Gesteira

Homologated Agreement IDN.A 23.
Approved Agreement ID10990.
Approved Agreement ID10993.
Approved Agreement ID NA 26.
Homologated Agreement ID NA 70.
Homologated Agreement - Catholic Church.
Homologated Agreement - Evangelical Church.
Approved Agreement - Funeral Chapel.
Approved Agreement - Soccer Field with Dressing Room.
Homologated Agreement - New Gesteira School.
Approved Agreement - Community Hall.
Homologated Agreement - WTP.
Approved Agreement - Seed Shed.
Homologated Agreement - Area for collective planting.
Approved Agreement - Bike path.
Approved Agreement - Hiking trail.
Approved Agreement - Fish Pit.
Homologated Agreement - Gymnastics Academy.
Approved Agreement - Support Space for Horseback Riding.
Approved Agreement - Playground for Children.

Paracatu de Baixo
Completion of Work on the Health Center.
Completion of Work on Santo Antônio Square.
Completion of Work on the Pre-K.
Completion of Elementary School.
Completion of Work on WWTP.
Completion of Work on WTP.
Completion of work on ID91A.
Completion of Work on ID28-UH.
Completion of work on ID103.
Completion of work on ID54.
Completion of work on ID52.
Completion of Work on ID28-UC.

Family

Homologation ID87.

Paracatu de Baixo

Completion of work on ID33.
Completion of work on ID60.
Completion of work on ID25.
Completion of work on ID37.

Bento Rodrigues

Work completion of ID 233.

Family

Completion of work on ID140
Completion of work on ID80.
Completion of work on ID91.
Property acquired with reform ID191.

Bento Rodrigues

Completion of work on IDCC.41
Completion of work on ID21C
Completion of work on ID217B
Completion of work on ID208-1.
Completion of work on the ID208-2.
Completion of work on the ID180A-1.
Finalization of work on the ID180A-2
Completion of work on ID126A
Completion of work on ID205
Completion of work on ID200
Completion of work on ID197
Completion of work on ID173
Completion of work on ID158
Completion of work on ID150
Completion of work on ID123
Completion of work on ID113
Completion of work on ID100
Completion of work on ID97
Completion of work on ID66
Completion of work on ID61
Completion of work on ID43
Completion of work on ID28
Completion of work on ID18
Completion of work on ID13
Completion of work on ID6
Completion of structuring batch IDCD17
Completion of structuring batch ID137C
Completion of structuring batch ID126B
Completion of structuring batch ID187
Completion of structuring batch ID162
Completion of the structuring of batch ID102
Finalization of the structuring of batch ID95
Completion of structuring batch ID2
Completion of work on Encontro Square (Collective Goods) IDNA8
Completion of work on the São Bento Central Square (Collective Goods) IDNA5
Completion of building work (New Centers) IDNN6

Family

Completion of work on ID306 (reconstruction)
Issued 16 occupancy certificates for buildings (new house, renovation, commercial and mixed)

Gesteira

Approval of the agreement ID NA 31
Approval of the agreement ID NA 81

Paracatu de Baixo

Completion of the building work (New Nuclei) IDNN30
Completion of work on ID51CC
Completion of work on ID77A
Completion of work on ID72B
Completion of work on ID57A
Completion of work on the ID40B (site)
Completion of work on ID131A
Completion of work on ID147
Completion of work on ID146
Completion of work on ID145
Completion of work on ID140
Completion of work on ID129
Completion of work on ID126
Completion of work on ID88
Completion of work on ID87
Completion of work on ID86
Completion of work on ID85
Completion of work on ID79
Completion of work on ID74
Completion of work on ID71
Completion of work on ID69
Completion of work on ID67
Completion of work on ID58
Completion of work on ID56
Completion of work on ID53
Completion of work on ID47
Completion of work on ID46
Completion of work on ID41
Completion of work on ID36
Completion of work on ID34
Completion of work on ID32
Completion of work on ID30
Completion of work on ID27

Bento Rodrigues

Completion of work on the ID190.
Finalization of work on the ID240.
Work completion of ID 74.
Work completion of ID 79.
Work completion of ID 93B.

Family

Completion of work on ID202
Completion of work on ID206
Completion of work on IDNN66

Gesteira

There were no relevant facts this month.

Paracatu de Baixo

Completion of work on ID102.
Completion of work on the ID29CC.
Completion of work on the ID40C.
Finalization of work on the ID65A

Bento Rodrigues

Completion of lot structuring service - ID 59A.
Completion of work on ID 21D-UH2.
Completion of work on ID CC.218.
Completion of work on IDs 135-UH1 and 135-UH2.
Completion of work on IDs 160.
Work completion of ID 04.
Work completion of ID 207.
Work completion of ID 218.
Work completion of ID 261.
Work completion of ID 35.
Work completion of ID 37.
Work completion of ID 77.
Work completion of ID 83.

Family

Completion of lot structuring service - ID 151.
Work completion of ID 87.

Bento Rodrigues

Work completion of ID 11A.
Work completion of ID 17A.
Work completion of ID 38.
Work completion of ID 42.
Work completion of ID 78.
Work completion of ID 93D1.
Work completion of ID 93D2.
Work completion of ID 126-1.
Work completion of ID 128.
Work completion of ID 147.
Work completion of ID 253.
Completion of the work on ID CC12.

Resettlement

Work completion of ID 126-2.

Family

Work completion of ID 220.

Gesteira

There were no relevant facts this month.

Paracatu de Baixo

There were no relevant facts this month.

Bento Rodrigues

• Work completion of the IDs below:
71-UH1
71-UH2"
• Delivery of work ID 93C
• Delivery of work ID 185
• Delivery of work ID 65
• Delivery of work ID 96
• Delivery of work ID 41
• Delivery of work ID 30
• Delivery of work ID 110

Family

Family
Delivery of works ID 130, 134 and 194.
Reconstruction
• Delivery of work ID 578.

Gesteira

There were no relevant facts this month.

Paracatu de Baixo

There were no relevant facts this month.

Resettlement

There were no relevant facts this month.

Bento Rodrigues

There were no relevant facts this month.

Family

There were no relevant facts this month.

Gesteira

There were no relevant facts this month.

Paracatu de Baixo

There were no relevant facts this month.

Mariana

There were no relevant facts this month.

Bento Rodrigues

There were no relevant facts this month.

Family

There were no relevant facts this month.

Gesteira

There were no relevant facts this month.

Paracatu de Baixo

There were no relevant facts this month.

Paracatu de Baixo

There were no relevant facts this month.

Gesteira

There were no relevant facts this month.

Resettlement

There were no relevant facts this month.

Bento Rodrigues

There were no relevant facts this month.

Gesteira

There were no relevant facts this month.

Paracatu de Baixo

There were no relevant facts this month.

Family

There were no relevant facts this month.

Resettlement

There were no relevant facts this month.

Bento Rodrigues

There were no relevant facts this month.

Family

There were no relevant facts this month.

Gesteira

There were no relevant facts this month.

Paracatu de Baixo

There were no relevant facts this month.

Resettlement

There were no relevant facts this month.

Bento Rodrigues

There were no relevant facts this month.

Family

General Monetary Payments (The calculation of proposals is being reviewed for later resumption of presentations - APRO 49):
Proposals submitted:
o 14 Monetary payment proposals accepted;
o 11 Monetary payment proposals paid;
o 03 Monetary payment proposals not yet paid;
o 08 Rejected monetary payment proposals.

Monetary payments New Cores: Proposals submitted:
o 05 Monetary payment proposals accepted;
o 02 Monetary payment proposals paid;
o 03 Monetary payment proposals not yet paid;
o 05 Rejected monetary payment proposals."

Property acquisition for ID SGC 42359 (Self-delimitation ID 186)
Information regarding the Self-Management Funds for New Houses, Reforms and Reconstruction
Numerical data on the number of houses ready for delivery:

New Houses: 05 services opted for funds for self-management;
Renovated houses: 02 services opted for funds to carry out the renovation;
Reconstruction: 01 service opted for funds for self-management.

Property acquisition for ID SGC 42446 (self-delimitation ID 110 ) delivery date 01/24/22
Property acquisition for ID SGC 42510 (self-delimitation ID 108 ) delivery date 01/24/22

Gesteira

There were no relevant facts this month.

Paracatu de Baixo

There were no relevant facts this month.

Resettlement

There were no relevant facts this month.

Bento Rodrigues

There were no relevant facts this month.

Family

There were no relevant facts this month.

Gesteira

There were no relevant facts this month.

Paracatu de Baixo

There were no relevant facts this month.

Family

Completion of works for ID 58.

Paracatu de Baixo

Start of works on ID 78.

Resettlement

There were no relevant facts this month.

Bento Rodrigues

Beginning of construction of 8 buildings by the company Cardan: ID's 173, CC.41, 226, 181 UH1, 181 UH2, 123, CC.123, NN.123

Family

ID 31 Received by the Family on 11/11/2021

Gesteira

There were no relevant facts this month.

Paracatu de Baixo

Beginning of construction of the buildings of ID's 37, 41 and 46.

Bento Rodrigues

Start of Cardan company activities on ID's 24 and 150.
Errata referring to the CIF of September_21:
Start of 2 houses of the new HTB amendment (IDs 135-1 and 135-2);
Errata referring to the CIF of September_21:
Beginning of 10 houses of the Cardan contract (ID's 61, CC137A1, 75, 81, 110, 210, 120A, 223, 225 and 182);

Family

Completion and delivery of the ID 307 reform.
Completion and delivery of ID 31;

Gesteira

There were no relevant facts this month.

Paracatu de Baixo

Mobilization of the Hexágono construction site.

Resettlement

Start of 8 houses of the new HTB amendment (Ds 135-1, 135-2, 21D-1, 21D-2, 74, 190, 261 and 93B);

Bento Rodrigues

Start works of 6 houses of the Cardan contract (IDs 61, 75, 81 210, 120A, 110);
Family

Completion of the second phase of the ID 351 renovation - Delivery of the property on 09/03/2021;
ID 031 - Works completed! Pending delivery to the family.

Gesteira

There were no relevant facts this month.

Paracatu de Baixo

Started paving the Main Access;
Start of construction of (ID's 27, 74, 80 and 84).

Resettlement

There were no relevant facts this month.

Bento Rodrigues

Start of 2 houses of the new HTB amendment (ID's CC.12 and ID 77);
Beginning of 4 houses of the Cardan contract (ID's 146A, 100, 113 and 98).

Resettlement

Acquisition of property (ID 41 - Pedras), on 07/23/21;
Property acquisition (ID 4 - Paracatu de Baixo), on 07/26/21;
Property acquisition (ID N.A.5 - Campinas), on 07/28/21;
Acquisition of property (ID 241 - Paracatu de Cima) on 08/02/2021;
Signed on 08/13/21 the Acceptance Term for the ID 390 Reform.
Activities started in ID 174 rural houses (on 08/02/21);
Completion of the second phase of the ID 351 reform – on 08/06/21. Property documentation pending for delivery to the family;
Stapled soil services (IDs 202 and NN.66) completed on 08/06/21;
Started the activities of ID 194* (on 07/16/21), ID 220 (on 08/05/21);
* Correcting the Relevant Facts from last month where we reported the starting date of ID 194 as 07/09/21, but the ID that started on that date was 140.

Gesteira

There were no relevant facts this month.

Paracatu de Baixo

There were no relevant facts this month.

Resettlement

Acquisition of property for Mrs. Sônia Aparecida Ferreira (ID 191), on 06/25/21, Family from Bento Rodrigues.
Acquisition of property for Mr. Cor Jesus Mol (ID 96A2), on 06/07/21, Family from Paracatu de Baixo.
Acquisition of property for Mr.. Wilson Miliano dos Santos, on 07/23/21, Family from Pedras.

Bento Rodrigues

Start construction of 6 houses of the new HTB amendment - (ID's 74, 190, 261, 21D(2 Houses), 93B

Family

Dynamic Company: Completion of the second phase of the ID 258 renovation – Sandra Polack. Property received by the family on 07/02/21.

Gesteira

There were no relevant facts this month.

Paracatu de Baixo

There were no relevant facts this month.

Resettlement

Social: Acquisition of property for Family Resettlement on 6/7 for Mrs. Sonia Aparecida
Social: Acquisition of property for Family Resettlement on 6/21 for Mr. Roberto Alves

Bento Rodrigues

Kickoff of Cardan Engenharia SA Company for the construction of 27 houses.
OS Issuance of 14 buildings for HTB

Family

Completion of the aviary works ID 247 by the company RMC. Property received by the family on 06/02/21.
Completion of the second phase of renovation ID 258-Sandra Polack by the company Dinamica. Checklist for final receipt in progress.

Gesteira

There were no relevant facts this month.

Paracatu de Baixo

Beginning of the water distribution network works.

Resettlement

Social: Remote assistance for families of resettlements continued;

Common Activities for All Resettlements

Logistics and material management for inventories;
Receiving aggregates and some materials such as: Gravel, Sand, Structural Blocks, Concrete Blocks, Curbs, Interlocking Pavers;
Continued preparing projects that can be carried out working from home;
Preparation of studies on the impacts of the COVID-19 pandemic;
Supply process negotiations / APRO’s;
Negotiation and alignment with stakeholders on actions to guarantee the safe resumption of activities;
Training for employees and third parties who are working from home;
The average absence rate under the contracted employees is 10%.

Bento Rodrigues

Completion of IDs 1 and ID 59.

Family

RMC Implementation: Completion of the aviary works ID 247. Checklist for final receipt of work in progress.

Deployment - Dynamica:
Completion of the second phase of the ID 258 renovation – Sandra Polack. Checklist for final receipt of work in progress.
Second phase of the ID 351 renovation in progress – Geralda Bartholomeu.

Deployment - Vina:
Issued the OS's referring to the executions of IDs 767, 7, 31, 58, 307 and 83.
The activities of ID 767, 58 and 307 are in progress.
Detailed schedules for IDs 767, 7, 31, 58, 307 and 83 are being prepared.

Deployment - Tecnosonda:
Execution of soil nailing services (IDs 202 and NN.66).
Kick-Off meeting held on 05/03/21.
Continuity in the mobilization process.

Acquisition of property for Mr. Diego Henrique Alves, on 05/06/21, Family from Bento Rodrigues.

Acquisition of property for Mrs. Maria do Carmo de Assis Gonçalves, on 05/10/21, Family from Pedras.

Supplies: Finalized the contracting process with Dinamica (Lage & Gomes) to carry out 5 urban renovations and 10 rural houses.

Gesteira

There were no relevant facts this month.

Paracatu de Baixo

Start of the deep drainage network in Areas 2 and 4.

Completion of the assembly of the prefab structure for the kindergarten and elementary schools.

Resettlement

Logistics and material management for inventories
Receiving aggregates and materials such as: Gravel, Sand, Structural Blocks, Concrete Blocks, Curbs, Interlocking Pavers.
Continued preparing projects that can be carried out working from home.
Preparation of studies on the impacts of the COVID-19 pandemic.
Supply process negotiations/APRO's
Negotiation and alignment with stakeholders on actions to guarantee the safe resumption of activities.
Training for employees and third parties who are working from home.
The average absence rate under the contracted employees is 10%.
Social: Remote assistance for families of resettlements continued.
Social: Remote assistance for families of resettlements continued.
Social: Property acquisition - ID 19 - Urban region of Paracatu de Baixo - Antonio Raimundo Teotonio.
Social: Property acquisition - N/A - Paracatu de Baixo (Rural) - Dan Mol Peixoto.

Bento Rodrigues

109 Statements of Acceptance were signed for Buildings and 18 for Vacant Lots.
Issued Permits: Permits were issued for 135 houses + 22 vacant lots + 4 Collective Goods. There are 15 houses with interrupted or replaced services + 4 vacant lots with interrupted or replaced services.

Family

PU: Vina - Conclusion of the contracting process for the execution of 6 renovations in the urban area. The company is in mobilization phase.
Engineering: The project (renovation) of Mrs. Maria do Carmo Pereira Ramos - ID83 at PMM, reference number 1765/2021, on 04/08/21.
Engineering: Issuance of building permit of Mr. Rodrigo Barbosa dos Santos, ID NN.66 on 04/16/21.

Paracatu de Baixo

3 Terms of Commitment were signed for Buildings.

Resettlement

Logistics and material management for inventories

Receiving aggregates and some materials such as: Gravel, Sand, Structural Blocks, Concrete Blocks, Curbs, Interlocking Pavers.

Continued preparing projects that can be carried out working from home.

Preparation of studies on the impacts of the COVID-19 pandemic

Supply process negotiations / APRO's

Negotiation and alignment with stakeholders on actions to guarantee the safe resumption of activities

Training for employees and third parties who are working from home

The average absence rate under the contracted employees is 10%.

SOCIAL

Remote assistance for families of resettlements continued;

Permission to continue assistance for 36 cases that were interrupted;

Permission to continue assistance for 36 cases that were interrupted;

10 appointments with Term 3 signatures (TAV) were released - Paracatu de Baixo;

Animal feed service transition, changing the format for families in temporary housing (previously receiving inputs, changing the format to financial value that generates autonomy for producers to manage their animals, as well as reducing costs on the part of Renova.);

64 Resettlement families, of which:
39 changed to receiving financial resources;
21 receiving inputs;
03 in the process of finalization;
01 Finished.

Bento Rodrigues

Completion of the Bridge (Sagrado Coraçao de Jesus Street) by - 03/27;

Started the construction of 42 houses (60 houses in total in progress).

Conceptual projects - Completed for 160 buildings, 19 vacant lots and 8 public goods;

Basic projects - Completed for 160 buildings, 19 vacant lots and 7 public goods;

Permits issued - For 124 buildings of the collective resettlement and 22 simplified licenses for vacant lots of the collective resettlement;

Statement of Acceptance - 109 were signed for Buildings and 18 for Vacant Lots.

Family

Approval of APROs. Renovation contract (Dynamic) and 10 rural houses;

PU - Mowing and maintenance of hoarding panels at the urban lots in Mariana;

RMC - Works on the aviary (ID 247) continued;

Hiring PU for detailing the projects with IDs 778 and 333.

Acquisition of property (lot) for Mr. Antonio Eloi de Paiva (ID-20B) on 03/11/21.

09 Completed Reconstructions;

04 buildings with detailed/individualized projects were completed;

01 buildings with detailed/individualized project in progress;

Gesteira

Acquisition of property for Mr. Jose Pinto on 03/10/21.

Paracatu de Baixo

Conclusion - Trench Containment.

Conceptual projects - Completed for 57 buildings, 4 vacant lots and 7 collective goods;

Permits were issued - For 7 buildings and 4 collective goods;

Terms of Commitment - 3 were signed for Buildings.

BENTO RODRIGUES

Started the construction of 14 houses
Bridge construction stages: Foundation piling, installation metal block frames; concretion of blocks

Area 2: Execution Plan for ID 65; ID21C; ID253, ID35; ID41; ID160; ID37; ID8A; ID7; ID4; ID78; ID79;

Started the construction of 14 houses;

Area 1: Execution plan for ID185; ID218.

PARACATU DE BAIXO

Started assembling the pre-molded structure of the schools.

There were no relevant facts in January.

Area 2: Containment of blocks F (ID 61) and D (IDs 21C, 249 and N.I.3); Foundation of ID 153 (Q. D1), Construction of houses IDs 01, 05, 11, 12 and 59; Masonry, installations, concreting, waterproofing, coatings and finishes of the school; Closing of the gym’s side wall; Installations and finishing of service and health posts; Construction of the shelter and execution of half round gutters and access ladder at the WTP; Drainage of lanes 22, 23, 25; ladder in lane 26; Soil nailing and blanket installation at ID 26.

Area 1: Drainage of lanes 18 and 12; Block I2 retainers (ID 313); and Foundation of ID 126 (Q. M1).

Area 3: Priming and HMA from access to well 5; Sewer system lane 10; and Containment of blocks O1 (IDs 90, 92, 93D, 96, 111 and 113) and N1 (ID 128).

Urban Distribution Network: Installations of luminaires and assembly of transformers.

Sanitary Landfill: operation; excavation and deposit of old garbage; blanket application at level 932; draining mattress and execution of drains at level 927; finishes and installations at the heavy vehicles warehouse.

WWTP: Curb, street gutter and access path; execution of HMA on the central lane; execution of new Jersey walls, geomembrane and ladder for lagoons; execution of reservoir pipes; and construction of the building.

ADME: Execution of gutters and land regularization.

Area 3 - Protection of plants around the access.

Completion of accumulated renovations of 05 urban buildings of which 3 were delivered to families.

Signed the acceptance agreement of property ID 780 - Silvania Aparecida de Souza, on 12/15/20.

Beginning of the mobilization of the company RMC - Hired to execute the Aviary in Santa Barbara-MG, to meet ID 247 - Nilton Calazans De Souza.

Commencement of construction on the vacant lot in urban area of Mariana-MG, to comply with ID 87A - Marcelo Jose Felicio."

Bento Rodrigues
Area 1 - Execution of superficial drainage of S.C. de Jesus (E.12 to 20); sewer from lane 15; drainage of lane 18; and containment of block I2 (ID 313)
Area 2 - Application of asphalt to the reservoir’s access road; stapled soil in lanes 19 and 22; and sewage network in lane 27; execution of the WTP rooftop; and execution of containments in blocks C, D, E, F, G.
Area 3 - Drainage of access to well 5; sewer of lanes 08 and 09; finishing of lanes 05 and 06; and earthworks and containments of IDs 90, 92, 93D and 96 (block O1).
Public Goods - Construction of the Public Goods - School, Service Center and Health Center is underway.
Houses - Completion of IDs 50, 64 and 112A. Works are underway in 5 houses of block F, IDs 01, 05, 11, 12 and 59.
WWTP - Completed the asphalt and the execution of curb, gutter, sidewalk and access drainage are underway; cutting, filling and construction of a geomembrane for the lagoons; and construction of the building;
Urban Distribution Network - Installation, equipping, laying of cables, assembly of traffic lights and fixtures on urban street light poles.

Paracatu de Baixo

Section A - Completion of Stapled Soil.

Branch A - Started Stapled Soil Containment.

Gesteira

Judicialization of the process regarding the Resettlement of Gesteira. Awaiting court decision to proceed with the service.

Família

Completion of bidding process for the construction of an aviary in Santa Barbara-MG.
Completion of 2 basic projects.
Completion of the area rectifications of 2 acquired properties.
Acquisition of 3 properties, vacant lot for construction of houses for 3 families that opted for this modality.

Assembly of the school's foundations completed.
Execution of activities on the Nailed Soil in Stretch A resumed.
Sewer and deep drainage on Monsenhor Horta Street completed.
Sewer and deep drainage in Santo Antônio Square completed.
Signature of 2 resentment adherence terms.
1 conceptual project completed.
The process related to the resettlement of Gesteira was judicialized. Waiting for a court decision to proceed with the services.
2 conceptual projects and 2 detailed projects completed.
1 basic project signed in the city hall
Acquisition of 2 properties for providing services, 1 for the construction of a new house, and 1 that will be repaired.

The installation of curbs and gutters for access to the wells in area 3 are underway.
Approval of the 6th organizational chart to increase more than 150 employees.
Completion of the installation and assembly of 181 street light posts of the 291 planned, and urban lighting cables.
Completion of 4 conceptual, 8 basic and 4 foundation projects.
The execution of lane 10 in area 3 is in progress.
Lanes 22, 25, 26, 27 and 28 are underway.
The installation of curbs and gutters for access to the wells in area 3 are underway.
Resumption of activities for the execution of stapled soil in section A.
Beginning of the assembly of the school's foundations.
Completion of the Gabion on Monsenhor Horta Street.
Completion of 2 conceptual and 14 foundation projects.
1st Resettlement Statement of Acceptance signed - ID 57A.
Judicialization of the process regarding the Resettlement of Gesteira. Awaiting court decision to proceed with the service.
Completion of 4 detailed projects.

Project Reconstruction of Bento Rodrigues
*Home office work for part of the Administrative personnel of Renova Foundation due to the guidelines of the World Health Organization (WHO) for containment of the virus COVID-19;
* Delay on the project's 2020 goals which will be reviewed after the return of activities paralyzed due to the COVID-19 virus;
* Conduction studies for the return of field activities in order to minimize the impacts on the project schedule and mitigate the likelihood of contamination of the collaborators of the work by COVID-19;
* Negotiations and alignment with stakeholders in order to ensure the return of activities safely;
* Ongoing plant suppression, topsoil cleaning and access earthwork, surrounding roads and facultative ponds for construction of the sewage treatment plant;
* Completion of the asphalt pavement of the Sagrado Coração de Jesus Street (est. 0 to est. 6) and subbase reinforcement (est. 6 to est. 15) in Area 1;
* Completion of the interlocked pavement of Alípio Viana and Conego Veloso streets and the launch of Conego Veloso's raw water network in Area 3;
* Completion of the installation of 165 urban lighting posts out of the 291 planned;
* Mobilization of the staff of the 5th approved tree (174 employees);
* Completion of the basic cemetery project;
* Completion of executive containment projects for 3 houses;
* Completion of executive foundation projects for 14 homes.
Baixo Paracatu reconstruction project
*Home office work for part of the Administrative personnel of Renova Foundation due to the guidelines of the World Health Organization (WHO) for containment of the virus COVID-19;
* Delay on the project's 2020 goals which will be reviewed after the return of activities paralyzed due to the COVID-19 virus;
* Conducting studies for the return of field activities in order to minimize the impacts on the project schedule and mitigate the likelihood of contamination of the collaborators of the work by COVID-19;
* Negotiations and alignment with stakeholders in order to ensure the return of activities safely;
* start of the building of the gabion at Monsenhor Horta street;
* Start of the building of the treated water supply;
* Beginning of trench containment;
* Conclusion longitudinal drainage of area 1;
* Mobilization of the staff of the 5th approved tree (55 employees);
* Completion of basic projects for 2 houses;
* Completion of executive foundation projects for 6 homes.
Gesteira Reconstruction Project
*Home office work for part of the Administrative personnel of Renova Foundation due to the guidelines of the World Health Organization (WHO) for containment of the virus COVID-19;
* Delay on the project's 2020 goals which will be reviewed after the return of activities paralyzed due to the COVID-19 virus;
* Negotiations and alignment with stakeholders in order to ensure the return of activities in a safe way;
Family Resettlement and Reconstruction project
*Home office work for part of the Administrative personnel of Renova Foundation due to the guidelines of the World Health Organization (WHO) for containment of the virus COVID-19;
* Delay on the project's 2020 goals which will be reviewed after the return of activities paralyzed due to the COVID-19 virus;
* Conduction studies for the return of field activities in order to minimize the impacts on the project schedule and mitigate the likelihood of contamination of the collaborators of the work by COVID-19;
* Negotiations and alignment with stakeholders in order to ensure the return of activities safely;
• Filled the simplified license to carry out the reform of the property of Ms. Edir Margarida dos Santos (PRO 4713/2020);
* Failure in the negotiation of the property intended for the family of Mr. Adriano Márcio Dias due to absence of financial agreement;
* Issue of 8 simplified licences;
* Acquisition of 2 properties;
* Completion of 1 conceptual project;
* Completion of 3 basic projects

Bento Rodrigues Reconstruction Project
• The Renova Foundation's administrative staff has been working from home due to the World Health Organization (WHO)'s guidelines to contain the spread of the COVID-19 virus.
• Committing to the project's goals for 2020, which will be reviewed after activities suspended due to the COVID-19 pandemic are resumed.
• Conducting studies for the resumption of field activities to minimize the impacts on the project’s schedule and mitigate the likelihood of contamination of the workforce by COVID-19.
• Communication and alignment with stakeholders to guarantee the safe resumption of activities.
• Completed the ID 57 roof and started installing the metallic structure of the ID 62 roof; Installed the paver installation in Carlos Pinto Street, Merces Street, and Nova 1 Street in area 1.
• Completed the pavement in Raimundo Muniz Street and Projected Street 3 in area 3.
• Started paver installation in Alipio Viana Street and Conego Veloso Street.
• The access layer to the wells is being treated, and the raw water network in Conego Veloso street and access to the wells have been released for operation.
• Completed the installation of 86 urban streetlights.
• Completed the conceptual project for 2 buildings.
• Completed the basic projects for 3 buildings, 2 vacant lots, and the Assembly of God Church.
• Completed the executive containment projects for 9 houses and 1 vacant lot.
• Completed the executive foundation projects for 6 homes.

Paracatu de Baixo Reconstruction Project
• The Renova Foundation's administrative staff has been working from home due to the World Health Organization (WHO)'s guidelines to contain the spread of the COVID-19 virus.
• Committing to the project's goals for 2020, which will be reviewed after activities suspended due to the COVID-19 pandemic are resumed.
• Conducting studies for the resumption of field activities to minimize the impacts on the project’s schedule and mitigate the likelihood of contamination of the workforce by COVID-19.
• Communication and alignment with stakeholders to guarantee the safe resumption of activities.
• Commencement of the sewage network works at the Santo Antonio Square.
• Completed the deep drainage of section B.
• Completed the basic projects for 1 house and 1 public good.
• Completed the executive foundation projects for 6 homes.

Gesteira Reconstruction Project
• The Renova Foundation's administrative staff has been working from home due to the World Health Organization (WHO)'s guidelines to contain the spread of the COVID-19 virus.
• Commitment to the project's 2020 goals will be reviewed after the resumption of activities suspended due to the COVID-19 virus.
• Communication and alignment with stakeholders to guarantee the safe resumption of activities.
• Continuation of the renegotiation of the land easement strip in Barra Longa, where the power line will be installed.
• Presentation of the Gesteira Conceptual Project in a virtual meeting held on 07/16/20 with the families of the Gesteira community to be resettled, the Commission of Affected Parties from Barra Longa, the Technical Advisory Service (AEDAS), the Socio-Environmental Studies and Research Group (GEPSA) of the Federal University of Ouro Preto (UFOP).
• Received a request by MPF/MPMG/SPU/DPEMG and its technical experts containing Ramboll's technical opinion on the Conceptual Project and a document containing contributions for discussion of the non-consensual guidelines. The document filed on 07/17/2020.
• Preparation of the basic infrastructure projects for the Gesteira Resettlement started on 06/30/2020.

Family Resettlement and Reconstructions Project
• The Renova Foundation's administrative staff has been working from home due to the World Health Organization (WHO)'s guidelines to contain the spread of the COVID-19 virus.
• Committing to the project's goals for 2020, which will be reviewed after activities suspended due to the COVID-19 pandemic are resumed.
• Conducting studies for the resumption of field activities to minimize the impacts on the project’s schedule and mitigate the likelihood of contamination of the workforce by COVID-19.
• Communication and alignment with stakeholders to guarantee the safe resumption of activities.
• Continuation of the discharge process of Andrade Gutierrez's workforce, and termination and removal of its equipment and installations.
• Acquisition of 1 property for the construction of a new house.
• Completed 1 executive project.

BENTO RODRIGUES
• The Renova Foundation's administrative staff has been working from home due to the World Health Organization's guidelines to contain the spread of the COVID-19 virus.
• Committing to the project's goals for 2020, which will be reviewed after the activities suspended due to the COVID-19 pandemic are resumed.
• Conducting studies for the resumption of field activities to minimize the impacts on the project’s schedule and mitigate the likelihood of contamination of the workforce by COVID-19.
• Communication and alignment with stakeholders to guarantee the safe resumption of activities.
• On 06/15, field activities resumed in compliance with the Technical Note issued by the Mariana Management Committee, which demanded adjustments to the resumption and diagnosis plan with fast COVID-19 testing for all mobilized employees. (1st, 2nd, and 3rd levels).
• On 06/26/20, the 3rd level received approval to mobilize 185 employees, now totaling 686. Before 03/23/2020, a total of 2207 employees were mobilized.
• Issuance of the environmental license for the Sewage Treatment Station, variant and other structures.
• Commencement of paver installation in Carlos Pinto Street in area 3.
• Commencement of paver installation in Raimundo Muniz Street in area 3.
• Commencement of excavation works for installation of posts for medium and low voltage electrical distribution network.
• Completion of the conceptual project of one building.
• Completion of the basic projects of four buildings.
• Completion of executive containment projects of 1 house and 1 vacant lot.
• Completion of executive foundation projects of 17 homes.
PARACATU DE BAIXO
• The Renova Foundation's administrative staff has been working from home due to the World Health Organization's guidelines to contain the spread of the COVID-19 virus.
• Committing to the project's goals for 2020, which will be reviewed after activities suspended due to the COVID-19 pandemic are resumed.
• Conducting studies for the resumption of field activities to minimize the impacts on the project’s schedule and mitigate the likelihood of contamination of the workforce by COVID-19.
• Communication and alignment with stakeholders to guarantee the safe resumption of activities.
• Recovery of the access road to Paracatu de Baixo began with the reparation of potholes.
• On 06/15, field activities resumed in compliance with the Technical Note issued by the Mariana Management Committee, which demanded adjustments to the resumption and diagnosis plan with fast COVID-19 testing for all mobilized employees. (1st, 2nd, and 3rd levels).
• On 06/26/20, the 3rd level received approval to mobilize 170 employees, now totaling 450. Before 03/23/2020, a total of 1080 employees were mobilized.
• Commencement of the execution of the foundation of the school.
• Completion of basic projects of 5 houses.
• Completion of executive projects for the foundations of 2 homes and 1 public facility.
GESTEIRA
• The Renova Foundation's administrative staff has been working from home due to the World Health Organization's guidelines to contain the spread of the COVID-19 virus.
• Commitment to the project's 2020 goals, which will be reviewed after the resumption of activities suspended due to the COVID-19 virus.
• Communication and alignment with stakeholders to guarantee the safe resumption of activities.
• CEMIG issued a memorandum in favor of electricity supply (300kVA transformer) at the construction site.
• The options for water supply systems were presented to the Barra Longa Commission of Affected Parties through a virtual session.
FAMILY RESETTLEMENT
• The Renova Foundation's administrative staff has been working from home due to the World Health Organization's guidelines to contain the spread of the COVID-19 virus.
• Committing to the project's goals for 2020, which will be reviewed after activities suspended due to the COVID-19 pandemic are resumed.
• Conducting studies for the resumption of field activities to minimize the impacts on the project’s schedule and mitigate the likelihood of contamination of the workforce by COVID-19.
• Communication and alignment with stakeholders to guarantee the safe resumption of activities.
• On 06/15, field activities resumed in compliance with the Technical Note issued by the Mariana Management Committee, which requested adjustments to the resumption and diagnosis plan with fast COVID-19 testing for all mobilized employees. (1st, 2nd, and 3rd levels).
• The 3rd level received approval on 06/26/20 to mobilize 45 employees, now totaling 110. Before 03/23/2020, a total of 232 employees were mobilized.
• On 6/15, the company Dinamica resumed the construction of 4 houses.
• Acquisition of 3 properties to attend the public of which 2 will be renovated and 1 will be build.
• Completion of 4 conceptual projects.

Bento Rodrigues Reconstruction Project
• The Renova Foundation's administrative staff has been working from home due to World Health Organization (WHO) 's guidelines to contain the spread of the COVID-19 virus.
• Committing to the project's goals for 2020, which will be reviewed after activities suspended due to the COVID-19 pandemic are resumed.
• On May 04, 2020, the Mariana Municipal Government authorized the local workforce to gradually resume work as of May 05, 2020.
• Technical recommendation No. 35 - COVID-19 was issued on May 21, 2020 by the Mariana Municipal Government, and prescribes the halt of all work until the Renova Foundation has complemented its action plan regarding COVID-19 prevention by testing the mobilized staff.
• Completing conceptual projects for three buildings and two public facilities.
• Completing basic projects for six buildings.
• Completing executive projects for containment for two homes and two empty lots.
• Completing executive projects for the foundations of two homes.
• Completing the Rua Ouro Fino pavement, and Rua São Bento asphalt.
• Finishing rain drainage from the Carlos Pinto, Nova 1 and Merces streets in area 1.
• 73 Conducting studies for resuming field activities in order to minimize the impact on the project's schedule and mitigate the likelihood of contamination of the workforce by COVID-19.
Paracatu de Baixo Reconstruction Project
• The Renova Foundation's administrative staff has been working from home due to World Health Organization (WHO) 's guidelines to contain the spread of the COVID-19 virus.
• Committing to the project's goals for 2020, which will be reviewed after activities suspended due to the COVID-19 pandemic are resumed.
• On May 04, 2020, the Mariana Municipal Government authorized the local workforce to gradually resume work as of May 05, 2020.
• Technical recommendation No. 35 - COVID-19 was issued on May 21, 2020 by the Mariana Municipal Government, and prescribes the halt of all work until the Renova Foundation has complemented its action plan regarding COVID-19 prevention by testing the mobilized staff.
• Completing conceptual projects for six buildings.
• Completing basic projects for three buildings.
• Completing executive projects for two homes' foundations.
• Conducting studies for resuming field activities in order to minimize the impact on the project's schedule and mitigate the likelihood of contamination of the workforce by COVID-19.
Gesteira Reconstruction Project
• Resettlement field activities have been interrupted since March 20, 2020, and the Renova Foundation's administrative staff has been working from home due to the guidelines of the World Health Organization (WHO) to contain the spread of the COVID-19 virus.
• Committing to the project's goals for 2020, which will be reviewed after activities suspended due to the COVID-19 virus are resumed.
• Delivering the final version of the Gesteira Resettlement Conceptual Project.
• The due dates for presenting and choosing alternatives for the resettlement's water supply system were set for May 06, 2020 and June 12, 2020, respectively.
Family Resettlement and Reconstructions Project
• The Renova Foundation's administrative staff has been working from home due to World Health Organization (WHO) 's guidelines to contain the spread of the COVID-19 virus.
• Committing to the project's goals for 2020, which will be reviewed after activities suspended due to the COVID-19 pandemic are resumed.
• On May 04, 2020, the Mariana Municipal Government authorized the local workforce to gradually resume work as of May 05, 2020.
• Technical recommendation No. 35 - COVID-19 was issued on May 21, 2020 by the Mariana Municipal Government, and prescribes the halt of all work until the Renova Foundation has complemented its action plan regarding COVID-19 prevention by testing the mobilized staff.
• Completing two conceptual projects and six basic projects.
• Acquiring two properties for service, one for new construction and one for renovation.
• Conducting studies for resuming field activities in order to minimize the impact on the project's schedule and mitigate the likelihood of contamination of the workforce by COVID-19.

Bento Rodrigues Reconstruction Project
• Resettlement field activities have been suspended since 03/20/2020, following the guidelines of the World Health Organization (WHO) to contain the spread of the COVID-19 virus. Therefore, the Renova Foundation's administrative staff has been working from home.
• Commitment to the project's 2020 goals, which will be reviewed after the resumption of activities currently suspended due to the COVID-19 virus.
• Completion of conceptual projects for 4 buildings and basic projects for 13 buildings.
• Completion of containment projects for 15 houses and 4 vacant lots.
• Completion of foundation projects for 5 homes.
• Conducting studies for the resumption of field activities to minimize the impacts on the project schedule and mitigate the likelihood of contamination of the workforce by COVID-19.

Paracatu de Baixo Reconstruction Project
• Completion of conceptual projects for 4 houses and basic projects for 8 houses.
• Completion of executive projects for foundations of 3 houses and the health center.
• Resettlement field activities have been suspended since 03/20/2020, and the Renova Foundation's administrative staff has been working from home due to the guidelines of the World Health Organization (WHO) to contain the spread of the COVID-19 virus.
• Commitment to the project's 2020 goals, which will be reviewed after the resumption of activities suspended due to the COVID-19 virus.
• Conducting studies for the resumption of field activities to minimize the impacts on the project schedule and mitigate the likelihood of contamination of the workforce by COVID-19.

Gesteira Reconstruction Project
• Resettlement field activities have been suspended since 03/20/2020, and the Renova Foundation's administrative staff has been working from home due to the guidelines of the World Health Organization (WHO) to contain the spread of the COVID-19 virus.
• Commitment to the project's 2020 goals, which will be reviewed after the resumption of activities suspended due to the COVID-19 virus.

Family Resettlement and Reconstructions Project
• Completion of 5 conceptual projects and seven basic projects.
• Resettlement field activities have been suspended since 03/20/2020, and the Renova Foundation's administrative staff has been working from home due to the guidelines of the World Health Organization (WHO) to contain the spread of the COVID-19 virus.
• Commitment to the project's 2020 goals, which will be reviewed after the resumption of activities suspended due to the COVID-19 virus.
• Conducting studies for the resumption of field activities to minimize the impacts on the project schedule and mitigate the likelihood of contamination of the workforce by COVID-19.

Bento Rodrigues Reconstruction Project
• 2nd asphalt layer on Sao Bento street (E.55 to E.80) and storm drain on Sagrado Coraçao de Jesus street.
• On 03/20/2020, due to guidelines from the World Health Organization (WHO) for containment of the COVID-19 virus, field activities were suspended and the Renova Foundation administrative staff started working from home, committed to the 2020 goals of the project, which should be reviewed after resumption of activities.
Paracatu de Baixo Reconstruction Project
• Completion of 2 conceptual projects and 9 basic projects.
• Issuance of 14 simplified foundation licenses.
• Completion of 4 headwalls.
• Completion of 37,000 m³ of earthworks.
• On 03/20/2020, due to guidelines from the World Health Organization (WHO) for containment of the COVID-19 virus, field activities were suspended and the Renova Foundation administrative staff started working from home, committed to the 2020 goals of the project, which should be reviewed after resumption of activities.
Gesteira Reconstruction Project
• Studies of technical alternatives for the water supply system in the resettlement were completed and submitted to the Barra Longa Commission of Affected Parties.
• On 03/20/2020, due to guidelines from the World Health Organization (WHO) for containment of the COVID-19 virus, field activities were suspended and the Renova Foundation administrative staff started working from home, committed to the 2020 goals of the project, which should be reviewed after resumption of activities.
Family Resettlement and Reconstructions Project
• The main building of Mrs. Maria Auxiliadora is ready for her family to be moved in.
• On 03/20/2020, due to guidelines from the World Health Organization (WHO) for containment of the COVID-19 virus, field activities were suspended and the Renova Foundation administrative staff started working from home, committed to the 2020 goals of the project, which should be reviewed after resumption of activities.

Bento Rodrigues Reconstruction Project
• Commencement of construction of the houses in block C.
• Commencement of remaining infrastructure works in Area 2.
Paracatu de Baixo Reconstruction Project
• Obtaining the General Property Registry (RGI) from the Registry of Deeds (Cartorio), totaling 175 registered properties.
Gesteira Reconstruction Project
• Filed document with the result of the 73 guidelines for the Resettlement of Gesteira, 21 without consensus, in the 12th Federal Civil and Agrarian Court of the Judicial Section of Minas Gerais.
• Completion and subsequent filing of the analysis of the Preliminary Draft of the Subdivision Project that integrates the Popular Resettlement Plan of the Collective Resettlement of Gesteira in the 12th Federal Civil and Agrarian Court of the Judicial Section of Minas Gerais.
Family Resettlement and Reconstructions Project
• Completion of three conceptual projects.
• Completion of a Service Order to start with the details to make 17 projects compatible.

Bento Rodrigues Reconstruction Project
• Completion of the 13.8 kV Transmission Line to Gate 1 of the resettlement.
• Foundation works started for id’s 68, 20 and 71 of block D1.
Paracatu de Baixo Reconstruction Project
• Completion of one foundation in area 1.
Gesteira Reconstruction Project
• 55 resettlement guidelines were discussed, including: 41 guidelines with consensus; 9 guidelines without consensus; 5 guidelines with proposed edited texts (under preparation).
• The resettlement of Gesteira was put on the ACP155bi agenda again to discuss the topics: resettlement guidelines, conceptual and urban design, type of land subdivision and deadline for carrying out these activities.
• Receipt of the preliminary project of the land subdivision for the collective resettlement that is part of the Popular Resettlement Plan for the Collective Resettlement of Gesteira.
Family Resettlement and Reconstructions Project
• There were no relevant deliveries and facts in January/2020.

Bento Rodrigues Resettlement Project
As of December 12, 107 houses, 13 vacant lots and 2 collective goods (school, health center, service center) were filed with Mariana’s Municipal Office, totaling 113 registered processes.
The infrastructure works (earthworks, subgrade preparation and paving), scheduled for 2019, have not been completed. Cause: The consortium formed with a local company underperformed, having completed approximately 55% of the 100% planned for the period. In addition, the volume of rainfall, expected to decrease in March 2019, remained high until May 2019, further contributing to reduce the pace of the works. Countermeasure: Transfer the remaining infrastructure works to the company HTB, which is larger and more experienced in conducting works of great complexity. This transfer was initiated in November 2019.
The construction of the service center and health center, scheduled for 2019, has not been completed. Cause: Delay in the approval process of the projects and in the issuance of building permits by Mariana’s Municipal Office. Countermeasure: An agreement was signed with Mariana’s Municipal Office, according to which the Renova Foundation would make professionals available to assist in the evaluation of registered projects, with the objective of providing greater speed in the permit approval process. The Renova Foundation is also undertaking ongoing efforts with Mariana’s Municipal Office to actively monitor permit issuance. Finally, the recent contracting of HTB for the execution of the mentioned buildings is also intended to contribute to the completion of this part of the scope.
The construction of 32 houses, scheduled for 2019, has not been completed. Cause: Insufficient time to complete the houses due to the delay in the approval processes of the projects and the issuance of building permits by Mariana’s Municipal Office. Countermeasure: An agreement was signed with Mariana’s Municipal Office, according to which the Renova Foundation would make professionals available to assist in the evaluation of registered projects, with the objective of providing greater speed in the permit approval process. The Renova Foundation is also undertaking ongoing efforts with Mariana’s Municipal Office to actively monitor permit issuance. Finally, the recent contracting of HTB for the execution of the mentioned buildings is also intended to contribute to the completion of this part of the scope. The houses are expected to be completed in December 2020, according to the construction schedule under discussion in a Public Civil Action.
Paracatu de Baixo Resettlement Project
Mariana’s Municipal Office issued the permit authorization to carry out subdivision works.
Completion of the installation of a fence around the entire perimeter of the subdivision.
Initiation of earthworks for the main access road to the Paracatu de Baixo Resettlement.
The external power grid that will supply the Paracatu de Baixo district has been completed.
As of December 2019, 32 conceptual house projects were completed, a fundamental item for the construction project.
The construction of equipment for collective use, planned for 2019, has not been started. Cause: Delay in the urban licensing (developmental approval) process. The projects were filed in February 2019 and only approved by Mariana’s Municipal Office in June 2019. Delay in the registration of the subdivision, considering that the descriptive memorandums were filed in August 2019 and that the respective decisions by Mariana’s Municipal Office have not been issued yet. Development of the urban project in conjunction with the community, whose participation took more time than initially planned. Countermeasure: Large company hired to execute infrastructure and buildings, due to its better execution capacity, in order to recover part of the delay generated in the issuance of licensing and in the registration of the subdivision.
Gesteira Resettlement Project
Signage of the land acquired for the implementation of the Gesteira Resettlement has been completed.
The infrastructure activities scheduled for 2019 have not started. Cause: Elaboration and approval of the Urban Project by the competent bodies, which are under the responsibility of the Technical Advisory Body, the Commission of Affected Parties and the Community, are still pending. Countermeasure: There is none, as it is necessary to wait for the referred urban project to be sent for analysis of technical and legal feasibility, as well as for the discussion, approval and carrying out of studies and projects and other actions necessary for the implementation of the resettlement.
Family Resettlement and Reconstructions Project
As of December 2019, 31 private instruments for the purchase and sale of real estate were signed.
CEMIG's analysis of the declaration of adverse possession of the property of P.M.D. was completed and approved.
Detailed projects for two buildings (ID 348 and 576) completed, documents necessary to start the construction of the building or renovation.

Bento Rodrigues
• On 11/01, the cables and installation of streetlights of the main access road (File 4) of the aerial distribution network was completed.
• On 11/01, the planned surveying for the Wastewater Treatment Plant (WWTP) was completed.
• On 11/01, the planned containments and foundations of Block F were completed.
• On 11/04, the interlocking pavement was completed in Nova 2 Street and Nova 5 Street of Area 2.
• On 11/13, the interlocking pavement in the Carlos Pinto Street of Area 2 - stake 18 to stake 29, was completed.
• On 11/21, the concrete station started operating to produce concrete on site for the construction of buildings.
• On 11/21, the “ComeSee” Resettlement Program was visited by the mayors of Mariana, Rio Doce and Baixo Guandu, in order to understand the challenges and to observe part of the repair work.
• On 11/27, the Technical Committee visited the Bento Rodrigues resettlement.
• On 11/29, the installation of the 130m³ drinking water reservoir was completed.
Paracatu de Baixo
• On 11/20, the trench slopes started to the covered with vegetation.
• On 11/21, the priest visited the lot of the Catholic Church.
• On 11/21, the maintainers visited the Paracatu de Baixo resettlement.
• On 11/23, the execution of the foundations of the houses began.
• On 11/29, soil nailing began at section A of the main access.
Gesteira
• On 11/12, an assembly was held with the community, AEDAS (State Environmental and Social Defense Association) and the Foundation to continue the discussion on guidelines for the resettlement.
Family Resettlement / Resettlement of Rural Communities (Reconstructions)
• On 11/01, the request for exemption of the environmental license for the property of M.J.A was filed.
• On 11/08, the contract for Fencing, Forest Restoration and Productive Restructuring was handed over.
• On 11/11, renovating of four houses began.
• On 11/19, the Fencing, Forest Restoration and Productive Restructuring contract was kicked off.
• On 11/27, two projects (fifth and sixth) for urban construction were filed at the Mariana Municipal Office.

Bento Rodrigues
• On 10/02, completion of the first action of the WWTP (Alternative 10) licensing process (Forest Inventory).
• On 10/02, initiation of containment works in blocks K and lanes 22 of area 1 and 23 and 24 of area 2.
• On 10/03, completion of drilling and reinforcement of the foundation piles of the Aterro administrative building.
• On 10/13, concreting of the holes of the foundations of the recycling depot and heavy vehicle parking.
• On 10/14, DEER approved the MG129 interchange project and consequently the revision of the environmental study to be filed with SEMAD was initiated.
• On 10/14, completion of the installation of the Sao Bento street HDPE drainage network.
• On 19/10, completion of the installation of the 40m³ elevated tank reservoir.
• On 19/10, completion of asphalt pavement of the main access.
Paracatu de Baixo
• On 10/01, completion of civil works of the headwalls of the stream crossing on Street 03.
• On 10/02, beginning of earthworks services in areas 2 and 4.
• On 10/11, completion of one headwall of the main access and one of Monsenhor Horta street.
• On 10/11, the first visit by those affected to the lot to validate the conceptual design.
• On 10/15, beginning of assembly of the stretch A reinforced earth retaining walls.
• On 10/19, completion of the power grid.
• On 10/21, release of descriptive memorandums of the lots by PMM.
• On 10/24, beginning of assembly of the stretch B reinforced earth retaining walls.
Gesteira
• On 10/17, a meeting was held with some of the heirs of the Barra Longa site, where the transmission line will pass, to begin negotiations on the right of way.
Family Resettlement / Resettlement of Rural Communities (Reconstructions)
• On 10/04, completion of purchase and sale agreement of Ms. Fatima Lucia Ferreira Moraes.
• On 10/06, resumption of the construction for Ms. Maria Auxiliadora.
• On 10/15, signing of the contract for Fencing, Forest Restoration and Productive Restructuring Services.
• On 10/16, the Mariana Municipal Office defined the need for a simplified license to start the renovation works.
• On 10/21, Filing of four renovation concepts with the Municipal Office/IPHAN, for issuance of a Simplified License.

BENTO RODRIGUES
• On 09/02, PMM mobilized professionals to analyze the basic projects of the buildings.
• On 09/03, the application of HMA asphalt in the main access started.
• On 09/10, the installation of the area 2 water network began.
• On 09/16, the earthworks and flexural wall of the lots in Area 1 began.
• On 09/18, completion of the top beam of the main access retaining wall 2.
• As of 09/20, the projects of 104 IDs, the school and the health center and services were registered, resulting in 98 registered projects and 31 analyzed projects. 18 permits have already been issued and 13 are in the process of validation.
• On 09/23, the 40m³ reservoir for the school arrived.

PARACATU DE BAIXO
• On 09/03, the school's conceptual project was presented to the Department of Education.
• On 09/10, the second infrastructure shift started work.
• On 09/12, plant suppression was completed.
• On 09/12, concrete headwalls were installed for the stream crossing of Street 03.
• On 09/18, the precast courtyard was installed.
• On 09/18, the Seculo XXI company responsible for fencing and plant suppression was dissolved.
• On 09/23, work began in two of the four residential areas.

GESTEIRA
• On 09/06, the engineering team analyzed the technical proposals for hiring the architects.
• On 09/16, resettlement signaling was completed by the Seculo XXI Company.
• On 09/17, a meeting was held with the community to align resettlement guidelines.

FAMILY RESETTLEMENT / RESETTLEMENT OF RURAL COMMUNITIES (RECONSTRUCTIONS):
• On 09/02, the conceptual / basic project for the renovation of the acquired properties was prepared.
• On 09/10, RFI occurred to continue the hiring process of hiring the architects.
• On 09/13, two basic projects were filed at PMM.

Bento Rodrigues:
• On 08/01, foundation works began for the service and health centers (Block C1).
• On 08/01, sixteen adhesions to the resettlement of Bento were signed, of the 17 permits already issued and which release the construction of residences.
• On 08/03, excavation began for the sheet piling of containment 2 of the main access.
• On 08/07, the company responsible for the construction of the oratory on the former Bento road was set in motion. Construction is expected to be completed on 09/10.
• On 08/12, paving began of the streets in the Camargos district.
• On 08/13, execution began of interlocking paving of Nova Street in area 2.
• On 08/19, execution began of the infrastructure of plateau 921 of the Sanitary Landfill.
• On 08/19, permit ID 79 was issued on behalf of Ms. Efigenia da Silva Felipe.
• On 08/22, priming of the primary access pavement between foundation piles 14 and 24 began.
• On 08/22, project planner Potamos presented the work plan for the access road to Camargos for evaluation by the Foundation.
• On 08/23, Bento Rodrigues' Collective Adhesion Agreement was signed by Ms. Efigenia da Silva Felipe.
• On 08/26, Tecnosonda started earthworks of Lane 19 in area 1.
• On 08/28, installation began of electric power grid posts at Bento's main access road, referring to File 4.
• As of 08/29, in Block F, 151 of 208 piled retaining walls and 331 of 384 m³ of concrete retaining wall were installed.
• As of 08/29, in Block F, 119 of 407 foundation piles were installed and, in the School, 319 of 435 foundation piles.
• As of 08/29, 158 out of 171 sheet piles for containment 2 of the main access were installed.
Paracatu de Baixo:
• On 08/01, a meeting was held between the maintainers and contractor Andrade Gutierrez to present the planning of the works.
• On 08/07, plant suppression of area 1 was completed.
• On 08/08, the descriptive memorandums of the lots were filed at the Municipal Office of Mariana, initiating the issuance process of the subdivision registration.
• On 08/08, execution began of the embankment of the main access.
• On 08/12, execution began of the culverts of the main access.
• On 08/13, a meeting was held to formalize the commencement of the works by Andrade Gutierrez.
• On 08/14, the assembly of VIVO's provisional cell phone tower began.
• On 08/14, the Commission of Affected Parties and the Technical Advisory Body visited the collective resettlement works.
• On 08/15, a Working Group was held in Mariana (MG) with the community of Paracatu de Baixo, with the purpose of evaluating available areas in the Urbanistic Project.
• On 08/22, preliminary services started in area 1.
• On 08/22, 3 Preliminary Service Orders (OSPs) were issued to Andrade Gutierrez:
- OSP # 001: installation of provisional and definitive construction site;
- OSP # 002: indirect team for the whole construction, and equipment for maintenance of service roads;
- OSP # 003: project design of main access, execution of main access, stream crossing and Area 1.
• On 08/22, the conversation circle methodology was validated to present the conceptual projects of collective facilities to the Paracatu de Baixo community.
• On 08/27, the maintainers made a visit to the construction site.
• As of 08/30, 43 pieces of equipment and machinery and 262 employees have been mobilized by Andrade Gutierrez.
Gesteira:
• On 08/02, all authorizations of the owners were collected to start the field survey work in order to gather information for the elaboration of the external power network project.
• On 08/07, land surveying with the use of instruments was completed.
• On 08/08, a general meeting was held with the community.
• On 08/12, inspections were carried out by Ultra in order to gather information for the design of the external power network project.
• On 08/12, the project and the descriptive memorandum of the construction site were delivered to initiate the license waiver request.
• On 08/12, the detailed MG-326 highway signaling project was sent to DEER for analysis.
• On 08/22, the company Ernst & Young made a visit to the area for an audit.
Family Resettlement / Resettlement of Rural Communities (Reconstructions):
• On 08/06, a hearing was held regarding the Public Civil Action in Mariana (MG).
• On 08/23, preparation began of the first 13 Reports on Potential Vulnerability of the families seeking financial compensation.
• On 08/27, the preliminary work plan, containing 8 urban houses, was presented by HTB.
• On 08/27, the construction company Geraes formalized its withdrawal from the reconstruction of Ms. Maria Auxiliadora house, due to financial imbalance, until 09/30/2019, if no commercial understanding occurs.
• On 08/29, conceptual and basic projects were sent to HTB for further studies to build 5 rural properties (4 reconstructions and 1 family resettlement).
• On 08/29, negotiations were finalized for acquisition of the property of Ms. Marimeire, opting for Family Resettlement.

Bento Rodrigues:
• On 07/01/19, a purchase order was released for the sheet piling for containments 2 and 3 of the main access, Piacentini company.
• On 07/08/19, a Kick-Off meeting was held with the Piacentini company for the execution of piled retaining walls at containments 2 and 3 of the main access. The preparation of the executive project is in progress.
• On 07/09/19, APRO was approved to contract the 2nd containment package with Tecnosonda.
• On 07/10/19, the Mariana Municipal Office released 12 building permits for houses; 10 for block F and 2 for block G.
• As of 07/12/19, the Mariana Municipal Office released 18 building permits; for 17 houses and the Municipal School.
• On 07/15/19, piled retaining walls of health and service centers were completed.
• On 07/18/19, alternative 10 was approved in a community meeting, a unique WWTP (lagoons system) in the region near ADME (topsoil deposit).
• On 07/18/19, the 1st order of sheet piling with ArcelorMittal was released, with the 1st delivery expected on 07/22.
• On 07/19/19, the piled retaining walls of the municipal school were completed;
• On 07/22/19, the execution of the foundations of the Municipal School began;
• On 07/23/19, the Piacentini company started the piling installation;
• On 07/23/19, a Kick-Off meeting was held with the Tecnosonda company, responsible for the containment of the blocks in areas 1 and 3;
• As of 07/23/19, 15 adhesions to the collective resettlement of Bento Rodrigues were signed, which release the construction of residences.
• As of 07/25/19, 4 house foundation works had been started.
• On 07/29/19, a contract was signed with HTB to build 231 houses, a school, churches, a soccer field, a sports court, a health center, service stations, a community center, water reservoirs, a sewage treatment plant, among other assets.
• On 07/29/19, construction began of the first house in Bento, located in block F.
Paracatu de Baixo:
• On 07/05/19, the specifications of the lots were delivered by Acta.
• On 07/10/19, the 7th General Meeting was held with 10 additional families to begin the elaboration of the conceptual designs of the houses.
• On 07/10/19, preliminary services began in section B (main access).
• On 07/11/19, plant suppression was completed at the wet passage.
• On 07/12/19, surveying activities were completed within the resettlement area.
• On 07/15/19, initiation of demarcation and preparation of the lots for visits by those affected and approval of the conceptual projects.
• On 07/17/19, the 8th General Meeting was held with 5 additional families to begin the elaboration of the conceptual designs of the houses.
• On 07/17/19, the removal of topsoil ADME 2 (main access) began.
• On 07/18/19, initiation of demolition of existing buildings in the resettlement area.
• On 07/18/19, initiation of mobilization of Andrade Gutierrez equipment and labor.
• On 07/18/19, the action plan of the project developer J + T was validated for the delivery of the conceptual and basic projects of the houses.
• On 07/24/19, the cleaning of topsoil in section A (main access) began.
• On 07/25/19, surveying at access road to Pedras was completed.
• On 07/25/19, APRO approval of the Andrade Gutierrez contract.
• As of 07/25/19, 74 conceptual house projects were underway and 14 had been completed.
• On 07/26/19, the cleaning of topsoil in section B (main access) was completed.
• On 07/29/19, the contract was signed with the company Andrade Gutierrez, responsible for infrastructure, construction of houses and collective equipment.
• On 07/30/19, excavation of the trench (main access) began.
• On 07/30/19, preliminary services started at the wet passage area (WWTP area).
• On 07/31/19, the 9th General Meeting was held with 7 additional families to begin the elaboration of the conceptual designs of the houses.
Gesteira:
• On 07/03/19, drilling equipment was mobilized for the 13 remaining drilling holes of this campaign that need to be done with instrumentation.
Family Resettlement / Rural Communities (Reconstructions):
• On 07/02/19, a meeting was held with Ultra to align Family Resettlement demands.
• On 07/05/19, initiated the rectification process at the Notary's office of the D. Oscar neighborhood.
• On 07/08/19, issued deed of adverse possession for J.G.C / M.H.F, as well as declaration of date of connection to power grid issued by Cemig.
• On 07/10/19, another key of the houses to be restored was handed to Engineering Reform (J + T), now in possession of 7 keys of a total of 8 properties.
• On 07/12/19, was collected from the legal team the environmental compensation agreement of M.A.
• On 07/19/19, negotiations were completed with Samarco for the acquisition of the Vargem e Goiabeiras Farm.
• On 07/23/19, presentation of the term for precautionary inspections in buildings adjacent to the Family Resettlement works.

Bento Rodrigues:
• On 06/03/19, the storm drains in Nova Street (Area 2) were completed.
• On 06/05/19, HTB signed a letter of intent for the construction of 230 houses, schools, two churches, soccer field, sports court, health center, community association, water reservoir, two sewage treatment plants, among other facilities. The construction company has 30 days, renewable for another 30 days, to sign the final contract.
• On 06/05/19, the sampling plan was issued to study the feasibility of building a cemetery on the institutional lot where today the visitor center is located.
• On 06/05/19, the APRO was approved for the landfill improvement works.
• On 06/06/19, the earthworks and containment projects for blocks F and G (Area 2) were filed.
• On June 06/07/19 and 06/14/19, the State Forestry Institute (IEF) visited the Bento Rodrigues construction site to evaluate additional areas of plant suppression, according to the need of the works, and for compensation areas.
• On 06/10/19, Enecon was hired, the second company responsible for monitoring the technological control and quality of the works.
• On 06/14/19, a technical visit was made with the companies for the execution of the Bento Rodrigues internal power distribution and network. The purpose of the visit was to present the scope and recognition of the project area.
• On 06/14/19, connection of household sewage pipes began with SAAE standard diameter of 100 mm.
• On 06/14/19, CEMIG approved the project for the electric power network for section 4, File 4 (section of the main access road of Bento Rodrigues).
• On 06/18/19, the storm drains in Dona Olinda Street (Area 2) were completed.
• On 06/18/19, the APRO of the additive of containment package 1 (PROGEO/AS consortium) was approved.
• On 06/18/19, two Work Orders (“OS”) were issued to the construction company HTB, which is responsible for the construction of the buildings. The OS authorized the mobilization of employees to carry out all activities related to the construction of 20 houses, schools, service stations and health centers.
• On 06/18/19, a WWTP workshop was held with the community of Bento Rodrigues.
• On 06/19/19, the company Vina was hired, responsible for the execution of the landfill improvement works.
• As of 06/19/19, the following were filed with the Municipal Office of Mariana: the basic project of the school, health and service centers and 76 basic projects of houses in Bento Rodrigues. Works will start with 61 of these projects, which are from priority areas.
• On 06/24/19, the execution of the provisional diversion of the construction site was completed.
• On 06/27/19, the second conciliation hearing was held at the 2nd Civil Court of Mariana County, in which the proposals for compensation and definition of the new location of the WWTP were presented. The community should decide in assembly on the location of the WWTP.
• As of 06/28/19, 345 foundation piles were completed for the school, 103 foundation piles for the health post, and the retaining walls of block F are under construction (ID112A, ID57, ID63, ID59, ID05 and ID62 - 79 foundation piles were erected and 86 m³ of concrete completed).
Paracatu de Baixo:
• On 06/03/19, workers were mobilized at the Paracatu construction site.
• On 06/04/19, a meeting was held with teachers on the methodology for developing the school project.
• On 06/05/19, plant suppression was approved in the Regional Conservation Unit (RCU).
• On 06/05/19, the building permit was issued by the Municipal Office of Mariana.
• On 06/05/19, a letter of intent was signed with Andrade Gutierrez for the execution of infrastructure works, houses and collective equipment.
• On 06/06/19, a prior meeting was held with the construction company Andrade Gutierrez.
• On 06/07/19, the first family visits to the sites began.
• On 06/12/19, the fencing of the polygonal area was completed.
• On 06/12/19, the 5th General Meeting was held with 10 more families to begin the process for developing the house projects.
• On 06/13/19, a Working Group was held to present the community's raw water studies.
• On 06/19/19, the 6th General Meeting was held with 10 more families to begin the process for developing the house projects.
• On 06/19/19, the definition of the prerequisites of the planning with Andrade Gutierrez began.
• On 06/19/19, the DAIA was issued.
• On 06/24/19, plant suppression began.
• As of 06/25/19, 65 families were ready to design the projects of the houses.
• On 06/27/19, a Working Group was held in which the Department of Education participated and in which the needs plan of the school was approved.
• On 06/27/19, the mobilization of Andrade Gutierrez equipment began.
Gesteira:
• On 06/01/19, the following were handed to the commission of affected parties: an official letter by the Renova Foundation containing an analysis of the guidelines, a descriptive report containing considerations on aspects related to the host area, as well as the inherent restrictions to the tract of land, which should be observed for the definition of the conceptual project.
• On 06/03/19, 37 boreholes were made without using instrumentation, for the preparation of preliminary studies.
• On 06/03/19, the fencing of the polygonal area was completed, except for the PPA areas.
• On 06/12/19, a technical visit was made to the Gesteira site by the RAF project planner.
Family Resettlement / Resettlement of Rural Communities (Reconstructions):
• On 06/07/19, the declaration of land tenure of the property of P.M.D was sent to Cemig to review the documentation.
• On 06/12/19, a technical visit was made together with a representative of the RAF company, regarding the hiring process for other family resettlement projects.
• On 06/12/19, a meeting was held to define the methodology for attending to the families in the category Family Resettlement Renovation.
• On 06/13/19, a meeting was held with Vaz de Mello, the company that issued the expert inspection reports, with the purpose of adjusting the information that is included in the report of the properties eligible for renovation.
• On 06/13/19, request for mobilization of architects for elaboration of one more project for “urban house construction” (J.G.O).
• On 06/18/19, a meeting was held with the Synergia team to monitor the Notebook design activities.
• On 06/19/19, the engineering team paid a technical visit to the properties.

Bento Rodrigues:
• On 05/07/19, CEMIG approved the project of the food network of stretch 2, File 2 (MG-129 to the Interchange of Bento Rodrigues).
• On 05/07/19, a workshop was held with those affected to discuss the operation and location of WWTP 2.
• On 05/13/19, the contention activities of Court F and the health center (UBS) began.
• On 05/14/19, excavation began for the sewage network (Nova Street) and execution of stretch 2 of the food networks (MG-129 to the Interchange of Bento de Rodrigues).
• On 05/14/19, the simplified construction permits for IDs 01, 05, 09, 44, 49, 252 and 112A were issued, releasing earthworks and containment activities.
• On 05/14/19, the Interdisciplinary/Housing WG was held on the studies regarding the WWTP location, the criteria for compensation, approval of the TAC and contracting of the companies for adjustments to the Bento Rodrigues landfill.
• On 05/18/19, the Family Festival was held at the new Bento site.
• Up to 05/31/19, the following were filed with the Municipal Office: the basic project of the municipal school; primary healthcare center and services; and 73 basic house projects in Bento Rodrigues. Of these projects, 57 are for the priority areas in order to start construction.
• Up to 05/31/19, 156 family visits were made to the lots, a necessary step to continue the development process involving the projects of the houses.
Paracatu de Baixo:
• On 05/02/19, a statement was released by the Municipal Council of Cultural Heritage (COMPAT) in favor of environmental licensing, with restrictions.
• On 05/07/19, a meeting was held with the State Water Management Institute of Minas Gerais (IGAM) to clarify the technical parameters used in the flow test and recovery of the well. However, even before such clarifications were given, the case was dismissed. The organ informed that it will be necessary to adapt the well and repeat the test in order to license the water withdrawal.
• On 05/08/19, a general meeting was held with 11 families to start the conceptual design of the houses.
• On 05/08/19, a legal statement was issued by the State Forestry Institute (IEF) requesting some documents referring to the Sete Saloes Park, a compensatory area for Atlantic Forest.
• On 05/09/19 a Working Group was held for a new discussion on the methodology for developing the projects of the houses. It was defined that the fair to choose the material for finishing touches will happen as part of the basic project.
• On 05/09/19, a meeting was held with the Secretary of Health for alignment on the plan of needs for the health center.
• On 05/13/19, the environmental licensing was issued by the municipality, with some restrictions.
• On 05/16/19, a Working Group was held to present the status of the environmental licensing and resettlement works.
• Between 05/14/19 and 05/17/19, technical visits were made to three tenderers who will participate in the bidding for contracting the infrastructure package, houses and collective equipment.
• On 05/17/19, the documentation requested by the IEF for the Sete Saloes Park, a compensatory area for Atlantic Forest, was filed.
• On 05/17/19, filed with IGAM the request for reconsideration the water withdrawal release from the well.
• On 05/21/19, authorization was issued for drilling an extra well.
• On 05/22/19, a general meeting was held with ten more families to start the process of designing the houses, totaling 43 families.
• On 05/29/19, the proposal for environmental compensation for the suppression of the Atlantic Forest in the Biodiversity Protection Board (CPB) was approved.
• On 05/30/19, a meeting was held with the Health Department regarding the health center project, with the participation of the Renova Foundation, Technical Advisory Body and community.
• On 05/30/19, authorization for wildlife management was issued by IEF.
• On 05/30/19, the Municipality of Mariana informed us that the Paracatu de Baixo urban project is eligible for approval and issuance of the building permit is scheduled for next week.
• On 05/31/19, interventions for the construction site were completed.
• As of 05/31/19, 43 families were eligible to develop the projects of the houses, of which 29 conceptual projects are already underway.
• On 05/31/19, three more architects of the J + T company were mobilized to prepare the projects for the houses, totaling 20 professionals.
Gesteira:
• On 05/08/19, a kick-off meeting was held with the company Ultra Energia, responsible for the external power supply network.
• On 05/08/19, a document was filed with the CIF, Technical Board, Prosecution Service, Commission of Affected Parties of Barra Longa and Technical Advisory Body, which expresses the concern of the Renova Foundation regarding the involvement of all in the restitution of the right to housing.
• On 05/09/19, the Renova Foundation presented the studies carried out in the host area to the community.
• On 05/09/19, the workflow of the stages of the rural land subdivision studies, with a projection of the expected duration by Renova to execute each phase, was filed with the Commission of Affected Parties of Barra Longa.
• On 05/14/19, the specialist in land parceling was hired.
• On 05/16/19, the meeting with the community of Gesteira was held with on the agenda the guidelines, conceptual project and workshops.
• On 05/20/19, a visit was made to hire the company that will be responsible for implementation of the planned scope of Gesteira.
• On 05/23/19, documents showing the restrictions/conditions of the land were handed to the community.
• On 05/30/19, water flow and water quality tests were received.
Family Resettlement / Resettlement of Rural Communities (Reconstructions):
• On 05/22/19, the Private Instrument of Commitment of Purchase and Sale of Real Estate Property (F.R.B) was signed.
• On 05/24/19, the Private Instrument of Commitment of Purchase and Sale of Real Estate Property (S.P.P.) was signed.

Bento Rodrigues:
• On 04/02/19, the basic project of the Municipal School of the new Bento Rodrigues was filed with the Municipal Office of Mariana.
• On 04/03/19, in regards of the Sanitary Landfill, the Municipality of Mariana informed that a licensing waiver will be issued for the installation of a construction site and initiation of works upon presentation of the conceptual plan of the construction site.
• On 04/04/19, initiation of the second round of infrastructure activities by the HSD consortium.
• On 04/12/19, CEMIG approved the food network project for stretch 1, File 1 (Stretch Alto do Rosario up to MG-129).
• On 04/23/19, the 16th Interdisciplinary/Housing WG meeting was held at the Convention Center of Mariana. Participating were the Prosecution Service, community of affected parties, Municipal Office of Mariana, technical advisory bodies, maintainers and the Renova Foundation. The next WG will be held on 05/14/19 at 5:00 p.m. The main points were:
Compensations: The Renova Foundation shall submit to MPMG (Prosecution Service of Minas Gerais), Commission and Advisory Board, within 7 days, a printed document containing a description of the compensation method, compensation scenarios with examples and values, applying the calculation methodologies presented, as well as examples to illustrate possible situations. Clear and practical language of how the formulas will be applied and their fundamentals. Deadline: 04/30/19;
Sanitary Landfill: The Renova Foundation must present the landfill project. Deadline: 05/06/19;
Location WWTP: Minutes of the March WG were not presented on 04/23. Resuming on 05/14/19.
• On 04/24/19, the retaining wall was completed in block F, corresponding to 3% of the total planned lot retaining walls.
• Up to 04/26/19, the following were filed with the Municipal Office of Mariana: the basic project of the Municipal School; of the Health and Service Center; and 46 basic projects of houses of Bento Rodrigues, of which 34 projects are for priority areas in order to start construction.
• Up to 04/26/19, a total of 146 family visits were made to the lots, a step necessary to continue the development process of the houses.
• On 04/29/19, scaffolding installation began at the Municipal School of the new Bento Rodrigues.
• On 04/30/19, construction of section 1 of the food network began (Stretch from Alto do Rosario to MG-129).
Paracatu de Baixo
• On 04/02/19, 11 registrations of the Certificate of Rural Property were filed at INCRA together with the Location Certificate to obtain the de-characterization of rural property. These are the 11 missing registrations out of a total of 16.
• On 04/02/19, a visit was made by the State Forestry Institute (IEF) to the Paracatu site to continue the evaluation of the process to obtain the plant suppression authorization.
• On 04/08/19, the environmental licensing was approved by CODEMA.
• On 04/09/19, a Working Group was held for discussions on the first general meeting to begin the elaboration of the conceptual projects of the houses and renovations of the church in the affected area.
• On 04/11/19, the first general meeting of 10 (ten) families was held to begin the process of elaborating the conceptual projects of the houses.
• On 04/12/19, all necessary alterations of rural property were issued by INCRA.
• On 04/16/19, the projects that were reviewed as requested by the Technical Note, including detailed infrastructure projects, were filed with the Municipal Office.
• On 04/16/19, families started to be interviewed for the development of the conceptual projects.
• On 04/16/19, the water and sewage projects were filed with SAAE.
• On 04/17/19, the revised EPIC and REPIC were filed with COMPAT, in compliance with the comments of the technical note received on 04/04 for further explanation and imposition of conditions, if any.
• On 04/17/19, documentation for requesting authorization for wildlife management was filed with SUPRI. On 04/26/19, additional documentation was filed.
• On 04/24/19, a meeting was held with the Department of Education, technical advisory body and representatives of the community to discuss the plan to meet the school's needs. A new meeting will be scheduled with the Health Care Secretariat to discuss the health center.
• On 04/24/19, the urban property registration of the Paracatu resettlement area was issued.
• On 04/25/19, a second general meeting was held with another 10 families to begin the conceptual design of the houses.
• On 04/26/19, the conceptual design of the landfill for construction waste, one of the determining factors for the approval of solid waste disposal, was filed with the Municipal Office of Mariana.
• As of 04/26/19, of the 20 families eligible to develop the projects of the houses, 9 have already started the interviews.
Gesteira
• On 04/02/19, a meeting was held with the Ministry of Regional Development (land, engineering and social), in Brasilia, for consultation on the resettlement of the communities affected by the Sao Francisco River transposition.
• On 04/12/19, an artesian well was drilled.
• On 04/15/19, a meeting was held with the community to clarify the necessary steps to move forward with the family resettlement process.
• On 04/16/19, the company Seculo XXI began to put up fencing around the polygonal area.
• On 04/26/19, the purchase order to contract the external power supply network was approved at all levels.
• On 04/30/19, the archaeological research on the Gesteira site was completed.
Family Resettlement / Resettlement of Rural Communities (Reconstructions):
• On 04/04/19, the Private Instrument of Commitment of Purchase and Sale of Real Estate Property - J. I. A - was signed.
• On 04/08/19, the Private Instrument of Commitment of Purchase and Sale of Real Estate Property - A.M.A - was signed.
• On 04/11/19, the Private Instrument of Commitment of Purchase and Sale of Real Estate Property - E.S. - was signed.
• On 04/22/19, delivery of the reconstructed house - W.P.
• On 04/24/19, the Private Instrument of Commitment of Purchase and Sale of Real Estate Property - J. J. A - was signed.

Bento Rodrigues
On 02/26/2019, the court established 08/27/2020 as the deadline for the delivery of the new housing in the resettlement.
On 03/07/19, approval was received from DEER in relation to the electric power project in stretch 2 (MG-129 to the Bento Rodrigues interchange).
On 03/14/19, the 6th General DSS was held at the construction site of the Bento Rodrigues resettlement. The meeting was attended by the employees of the companies involved in the construction of the project and the Renova Foundation. Relevant issues regarding recycling and correct selective collection (presentation by the Mariana Association of Collectors of Recyclable Material - CAMAR), clarification on the financial health of the HSD consortium (responsible for the Bento Rodrigues infrastructure) and clarification on the correct dissemination of information on the progress of the Bento Rodrigues works.
On 03/14/19, the commission of affected parties visited the resettlement of Bento Rodrigues for photographic registration and verification of the progress of the works.
On 03/18/19, the records of the Bento Rodrigues resettlement lots were completed.
On 03/22/2019, the analysis began of the technical proposals for the sanitary landfill.
Up to 03/22/19, 53 probing holes were drilled, of the 250 holes anticipated in total, for execution of the geological model and sections, preparation of the projects for retention of the subdivision.
Visits of the families to the lots continue, to follow the development process of the housing projects. A total of 129 visits occurred up to 03/22/19. Present at these visits are affected families, technical advisory body, Social Management team, team that will execute the works, and the architect who elaborated the project of the house with the family.
Paracatu de Baixo
Up to 03/22/19, 11 probing holes were drilled, out of the total 45 of this campaign, for the elaboration of infrastructure projects.
On 03/08/19, five of the 16 pending de-characterizations of rural properties were filed with INCRA. Of these, 11 registrations were still pending, since the Rural Property Certificates were issued with other codes than on the Location Certificate.
On 03/12/19, the electrical and hydro-sanitary installations at the main gate and support center for those affected were completed.
On 03/14/19, the installation of the roof tiles to cover the cafeteria of the construction site was completed.
On 03/19/19, Cemig turned off the power to enable the installation of the capacitor bank and recloser, to provide service through the new electricity grid that will power the subdivision. On 03/21/19, the transformer of the provisional network was installed.
On 03/19/19, the urban planning projects were submitted to the Municipality of Mariana, with a geometrical review of the lots (after analyzing the mapping survey).
Gesteira
Up to 03/22/19, four probing holes were drilled, out of the 50 in total, for the elaboration of infrastructure projects.
On 03/11/19, a land record was issued on behalf of the Renova Foundation.
On 03/13/19, a kick-off meeting was held with Seculo XXI, a company contracted to execute the fencing of the land (polygonal). On 03/19/19, the company made a visit to the Gesteira site to acknowledge the area.
On 03/14/19, Samarco visited the Gesteira site for locating the enclosure in the interference area with the mineral slurry pipeline.
On 03/18/19, a meeting was held with the community to discuss the topics Emergency Financial Aid and mediated indemnity.
On 03/21/19, a meeting was held at the Town Hall of Barra Longa regarding the preliminary consultation on rural land parceling for the Gesteira site.
Social
Throughout this month, the Working Group held three meetings. On 02/28/19, the Landscaping Project was presented, featuring alterations made based on the results of the roundtable discussions for those affected in Paracatu de Baixo, in addition to a presentation of the paving and WWTP projects. On 03/14/19, discussions were held on the deadlines for resettlement and the projects mentioned. On 03/19/19, discussions were held on the assembly for approval of these projects.
On 02/25/19, a carnival mask workshop was held at RECRIAVIDA with a group of elderly and family members that will take part in the resettlements.
On 02/26/19, a meeting was held with the community of Gesteira to present and debate on the next steps of the resettlement. The community, supported by its technical advisory body, defined that the parceling of the soil of the resettlement will be rural.
On 02/27/19, a carnival workshop was held at RECRIAVIDA with a group of elderly and family members that will take part in resettlements.
On 03/12/2019, the 15th Interdisciplinary/Housing WG was held at the Convention Center of Mariana. Participating were the Prosecution Service, community of affected parties, Municipal Office of Mariana, technical advisory bodies, maintainers and the Renova Foundation. The main points were:
- The technical advisory body presented the result of the meeting held on 02/26/19, to define the time frame of the new centers.
- Verification of the possibility for a greater distance between the houses and the WWTP location.
- The Prosecution Service requested a detailed letter from the Municipal Building Department stating the insufficiency of professionals in this department.
- The Prosecution Service requested to submit a preliminary compensation proposal for the differences between the original real estate and the intended resettlement type.
Scheduled for 04/23/19, the next meeting of the Interdisciplinary/Housing WG.
In the week of 03/18/19 to 03/22/19, the terms necessary for the collective resettlement of Bento Rodrigues were finalized.
In the week of 03/18/19 to 03/22/19/19, the Family Social Assistance and Support Plan - pre-housing and post-occupation stages was completed.

Bento Rodrigues
The environmental study was completely revised and finished on 02/10/19 to release works in specific locations that extrapolate the licensed area. The evaluation of the technical proposals for the construction of the Sanitary Landfill was completed on 02/15/19.
CEMIG issued a report on 02/18/19 approving the projects of the urban electricity grid / public lighting of the Bento Rodrigues resettlement.
Earthworks for the access road to the Bento Rodrigues subdivision began on 02/19/19.
The first technical proposal of one of the proponents for the execution of package 1 for the construction of houses was presented on 02/26/19.
The projects of the urban electricity grid / public lighting of the Bento Rodrigues resettlement, in compliance with the conditions of the permit, were filed with the PMM on 02/27/19.
Visits of the families to the lots continue, to follow the development process of the housing projects. A total of 106 visits occurred up to 03/08/19. Present during these visits are the affected families, technical advisory body, Social Management team, team that will execute the works, and the architect who elaborated the project of the house with the family.
So far, 35 probing holes were drilled (of the 250 holes planned in total) for execution of the geological model and preparation of the containment projects of the subdivision.
Power is up and running, the electric power grid put into operation and the lighting system installed at the construction site.
Paracatu de Baixo
The Municipality of Mariana issued the Location Certificate of the subdivision on 02/18/19.
The Secretariat of Environment visited the area of Paracatu de Baixo on 02/18/19 to continue the evaluation for environmental licensing.
The Municipality started analyzing the projects for developmental approval and licensing on 02/21/19.
On 02/22/19, an official letter was filed with the Commission of Affected Parties with a definitive date for the presentation of conclusive studies on the raw water supply.
On 02/26/19, the earthworks in the area of the cafeteria were completed and the execution of the walls of this space were initiated.
On 02/27/19, the drilling of probing holes began for the elaboration of the infrastructure projects.
On 02/28/19, a Working Group was held to present the paving, landscaping and WWTP projects.
Gesteira
On 02/13/19, a meeting was held with Emater for negotiations on the types of land subdivision.
On 02/14/19, a visit was made to the Gesteira area with a team from the Internal Work Group of the Renova Foundation to learn about the resettlement land.
On 02/20/19, the preliminary studies of the host area were resent to the Commission of Affected Parties and technical advisory body.
The details of the next steps of the Gesteira resettlement were filed on with the Commission of Affected Parties and technical advisory body on 02/22/19.
On 02/26/19, the drilling of probing holes began for the elaboration of the infrastructure projects.
On 02/26/19, a meeting was held with the community to present and debate the next steps of the resettlement. The community, supported by its technical advisory body, defined that the parceling of the soil of the resettlement will be rural.
Social
On 09/02/19, a mass was held in the area of the Paracatu de Baixo resettlement.
On 02/12, 02/13 and 02/14/19, WGs presented the points identified in the roundtables (validation of the landscaping, paving and WWTP projects) and evaluation of the activities carried out during the roundtables for Paracatu de Baixo.
On 02/19/19, the WG discussed the format of the feedback on the roundtables (validation of landscaping, paving and WWTP projects) for Paracatu de Baixo.
On 02/25/19, a masks workshop was held at RECRIAVIDA with a group of elderly of the resettlement and their relatives.
On 02/26/19, a meeting was held with the community of Gesteira.
On 02/27/19, a Carnival workshop was held at RECRIAVIDA with a group of elderly of the resettlement and their relatives.
On 02/28/19, the landscaping project was presented, which included alterations made after the roundtables with those affected from Paracatu de Baixo.
In February, the terms of the resettlement were approved by the Prosecution Service. Also approved was the hiring of the resettlement consulting firm.
On 03/12/2019, the 15th Interdisciplinary/Housing WG was held at the Convention Center of Mariana. Participating were the Prosecution Service, community of affected parties, Municipality of Mariana, technical advisory bodies, maintainers and the Renova Foundation. The following points were discussed:
the technical advisory body presented the result of the meeting held on 02/26/19 to define the time frame of the new centers;
verification of the possibility for a greater distance between the houses and the WWTP location;
the Prosecution Service requested a detailed letter from the Municipal Building Department stating the insufficiency of professionals in this department;
the Prosecution Service requested to submit a preliminary compensation proposal for the differences between the original real estate and the intended resettlement type.

Bento Rodrigues
The projects and documentation related to file 3 (Bento Rodrigues intersection at the Mariana landfill) to prepare the electrical grid for the Bento Rodrigues resettlement were approved by CEMIG on 01/03 and works were initiated on 01/08.
The report on emergency intervention works at the Mariana landfill for the rainy season was filed on 01/07 with the Municipal Office of Mariana.
Activities for implementation of storm drainage in area 2 of the Bento Rodrigues resettlement project were started on 01/09.
Held on 01/15, at the Convention Center of Mariana, the 14th Interdisciplinary/Housing Working Group with participation of the Prosecution Service, community of affected people, Municipal Office of Mariana, technical advisory bodies, maintainers and the Renova Foundation. Discussed were the resettlement of new households, dealing with the inconsistencies between boundary limits and auditing, environmental and urban licensing of Paracatu de Baixo, status of the collective resettlement works of Bento Rodrigues, Paracatu and Gesteira. Also addressed were questions related to the visits to the host land by those affected, family resettlement and a descriptive memorial of the Bento site. The next meeting of the group was scheduled for 03/12/2019.
Held on 01/16, the 5th General Health and Safety Dialogue at the construction site of the Bento Rodrigues resettlement. The meeting was attended by all employees and companies involved in the construction of the project and employees of the Renova Foundation. Relevant safety issues were addressed with a training on the interaction man vs. machine.
Completed on 01/19, the wiring of the electricity grid, part of file 3 (Bento Rodrigues interchange at the Mariana Sanitary Landfill).
The visits of the affected families to the Bento Rodrigues site resumed on 01/22. Present at these visits will be affected families, technical advisory body, Social Management team, team that will execute the works and the architect who elaborated the project of the house with the family.
The purpose of these visits is to give each affected family the opportunity to get to know the area where their house will be built, to clarify existing doubts with the teams and to continue the elaboration process of the project.
The activities of installing posts, cables and equipment for the electricity grid, part of file 5 (Ouro Preto interchange), were completed on 01/28.
On 01/28, the project and other documents related to the property with the name “Resettlement of Bento Rodrigues" were published in Mariana (MG) by the Registry of Real Estate. The requirements, exemptions, prohibitions and caveats, including indications for each lot contained in the memorial shall be an integral part of the registration and shall be entered in their respective field.
The Prosecution Service and technical advisory body Caritas have approved 16 resettlement terms that will be used for those affected. New terms that are needed during the course of the resettlement will be elaborated and re-validated.
On 02/04, the drilling began of the 250 probe holes based on the technical study of BVP Engineering to define the geotechnical profile of the project.
Paracatu de Baixo
Signing of the contract of CHD Consortium on 01/07. On the same date, the request for a location certificate in the Municipality of Mariana was also filed and an ambulance was mobilized for the resettlement of Paracatu de Baixo.
On 01/14, Engelig started its activities and CHD consortium, responsible for the construction site, started its fieldwork.
On 01/16, the basic urban projects were filed at the Secretariat of Works for developmental approval.
On 01/18, the methodology for approval of the landscaping, paving and WWTP projects was validated by the community of Paracatu de Baixo.
On 01/29, Engelig started the installation of posts for the main line of Paracatu de Baixo.
On 01/30, environmental studies and projects to obtain the environmental license were filed with the Environmental Department.
On 01/05, 01/06 and 01/07, open discussion sessions were held with the community about landscaping/ paving/ water supply and sewage treatment.
On 02/05, the request for environmental intervention in the area of the Paracatu de Baixo resettlement was filed with SEMAD.
Gesteira
On 01/14, the registration of the land of the Gesteira resettlement was rectified at the Registry of Real Estate.
On 01/17, the ITBI (Property Transfer Tax) was paid for the Gesteira land.
On 01/18, dispensation was granted by the Municipal Government of Barra Longa for the licensing concerning the opening of the access roads to the Gesteira site and probing services on the land.
On 01/29, the purchase and sale agreement of the Gesteira land was signed.
Social Management
Between 01/05 and 01/11, progress was made in the hearings with the families of Bento Rodrigues; progress in discussions with Technical Advisory Body about lot size; elaboration of the proposal of the methodology for presenting and validating the projects for the community of Paracatu de Baixo (landscaping, urbanization and WWTP); APRO technical analysis of the draft of the Gesteira resettlement agreement; the terms for collective and family resettlement were validated (even the release for construction, but those related to the execution of the work are still pending); progress in drafting the compensation proposal.
Between 01/12 and 01/18, progress was made in the hearings with the families of Bento Rodrigues; critical case analysis (1st committee); progress in discussions with Technical Advisory Body about lot size; progress in the construction of the compensation proposal and time frame for family dynamics; Reparation WG in Mariana (center and rural area); release resumption of visits to lots in Bento Rodrigues.
Between 01/19 and 01/25, progress was made in the hearings with the families of Bento Rodrigues; critical case analysis (2nd committee); progress in the construction of the compensation proposal and time frame for family dynamics; approved was the methodology for presenting and validating the projects for the community of Paracatu de Baixo (landscaping, urbanization and WWTP).
Between 01/26 and 02/01, progress was made in the hearings with the families of Bento Rodrigues; progress in the construction of the compensation proposal, new center, granted, multifamily lots and time frame for family dynamics; finished the documentation of the methodology for presenting and validating the projects for the community of Paracatu de Baixo (landscaping, urbanization and WWTP) in open discussion groups; meeting with Prosecution Service to validate the terms to be used for the resettlement.
Between 02/02 and 02/08, progress was made in the hearings with the families of Bento Rodrigues; progress in the construction of the compensation proposal, new center, granted, multifamily lots and time frame for family dynamics; open discussions for presentation and validation of the projects to the community of Paracatu de Baixo (landscaping, urbanization and WWTP); validation of terms to be used in resettlement by Prosecution Service; revised the family resettlement procedure; revised the resettlement policy.

Bento Rodrigues:
- Completion of the power line of the construction site
- Completion of construction sites
- First visits by the affected people to the allotment
- Completion of the enclosure
- Completion of emergency works at the sanitary landfill

Paracatu de Baixo:

- Filed the 2nd Bill of Paracatu de Baixo with the Municipal Council
- Publication of the 2nd Bill of Paracatu de Baixo by the Municipality of Mariana
- Land registry on behalf of the Renova Foundation

Gesteira:

- Acquisition of land for resettlement

On 01/11, the cafeteria of the Bento Rodrigues resettlement construction site was inaugurated with a special lunch. The event was attended by employees of all contractors and the Renova Foundation. From now on, employees don’t need to leave the premises anymore to have lunch.
On 06/11, we received formal authorization from the Mariana Municipal Office for emergency intervention at the municipal landfill to carry out protective measures in order to minimize instability risks during the rainy season. That same day, we completed the topographic signage of the lots located in blocks C, D, E, F and G in area 2. This activity will facilitate the identification of lots during the visits that will be made by those affected, and also for earthworks.
On 11/07, transportation began of the firewood donated to the affected families, as requested by the community of Bento Rodrigues. Part of the wood material extracted from the subdivision was reserved for this request, the other part is used for fencing the subdivision.
On 11/07, the following were completed at the earthworks construction site: the support structures of the toolroom/warehouse, workshop, carpentry unit and waste unit.
On 11/07, the Descriptive Memorandum of the Bento Rodrigues lots was filed at the Mariana Municipal Office. This was necessary to proceed with the issuance of the individual General Property Registry for each lot, which is a condition for the developmental approval of the Bento Rodrigues works.
On 11/07, 11/08 and 11/09, visits were made to the Bento Rodrigues resettlement subdivision by the architects who are preparing the individual projects of the houses. At a meeting held on 11/08, the latest adjustments were made for the visit of the Commission of the Affected Parties in conjunction with the Social Management team. Activities such as demarcation of lots with zebra tape, creation of schedule and route, and definition of safe paths were completed. The visits will be carried out according to the weather conditions and the possibility to move around on the construction site in safe conditions, due to the high change of rainfall in that period.
On 11/08, the tree felling provided for in the initial suppression map was completed. Suppression activities will now proceed with the felling required for drainage activities.
On 11/09, the MG129 Interchange Improvement Project was filed with the DEER in Ponte Nova. The project provides for improved access to the Bento Rodrigues subdivision.
On 11/13, initiation of emergency intervention works at the sanitary landfill of Mariana during the rainy season for adoption of protective measures. The goal is to minimize the instability risks at the site.
On 11/14, the 3rd General DDSS was held at the Bento Rodrigues Resettlement Construction Site. The meeting was attended by all employees and companies involved in the construction of the endeavor, and employees of the Renova Foundation. Addressed were relevant topics in relation to safety and the importance of the commitment of all in the execution of the project to reestablish the lives of those affected.
On 11/19, billboards were installed for identification of the lots where the Municipal School, the square, the service center and the health center of Bento Rodrigues will be built. This signage will help recognizing the areas during the visits to the subdivision.
On 11/20, the topographic marking of the lots in block E was completed, finalizing the topographic marking of the lots in area 2.
On 11/22, works for the implementation of the provisional power grid for the Bento Rodrigues resettlement construction site began. The provisional grid will replace the generators currently used on the site.
On 11/26, there was a Working Group with those affected from the community of Bento Rodrigues to present the status of the selection process of the company responsible for building the first resettlement houses and public assets. Of the 60 companies that started the process, only 6 reached the final phase. On 12/04, an assembly will be held with the community to select the company and to define contracting.
On 11/28, a Working Group was held for in-depth discussion of the interpretation of the guidelines that defines the concept of new households and initial criteria for priority choice of lots in Bento Rodrigues. The Renova Foundation and The Caritas Foundation presented their opinion. On 12/11, a new meeting will be held to define one single concept.
On 11/29, the provisional access road to the ADME (Surplus Material Deposit Area) was completed. Now, all surplus material for the landfill will be allocated to that area, where the Bento Rodrigues resettlement soccer field will be implemented in the future.
Paracatu
Consent was received for collection and disposal of solid waste for the Paracatu de Baixo resettlement, issued by the Municipal Secretariat of Works on 11/09.
Completed the works to improve access to the Paracatu de Baixo subdivision, Furquim Street section, on 11/09.
A Working Group was held with the Commission of Affected Parties of Paracatu, G20 and Technical Advisory Body (Caritas) for general assessment of the house design methodology on 11/08. It was agreed that on 11/14, there will be a presentation on the progress made with the conceptual project, for environmental and urban licensing purposes, and approval of the Bill for the creation of a Special Guidelines Area, for the implementation of the Paracatu de Baixo resettlement.
The purchase and sale agreement of Joao Taborda land was signed on 11/09. This area will be needed to carry out works to improve the access to the Paracatu de Baixo resettlement.
A meeting was held with the Mariana Secretariat of Works on 11/13 to define the level of the basic projects for developmental approval purposes.
HD (Hexagon + Dynamic) Consortium was set up for the implementation of the Paracatu de Baixo construction site on 11/20.
License obtained by the Mariana Municipal Office for construction of the Paracatu de Baixo construction site on 11/20.
On 11/21, a meeting was held to discuss the draft of the Bill establishing and regulating the ADIES (Special Guidelines Area) for the Paracatu de Baixo resettlement, between the Municipal Office, the Public Prosecution Service, SECIR, the community, Technical Advisory Body and the Renova Foundation.
The content of the Bill of ADIES (Special Guidelines Area) for the Paracatu de Baixo resettlement was consolidated on 11/22.
On 11/24, works were initiated for implementation of the Paracatu de Baixo construction site through a contract established through PG010. Completion is expected for March/19.
On 11/27, a Public Hearing was convened by the Mariana Municipal Office to discuss the ADIES Bill, to be held on 12/07.
On 11/27, kick-off of HD (Hexagon + Dynamics) Consortium, responsible for the implementation of the Paracatu de Baixo construction site.
Fencing of the Paracatu de Baixo resettlement area started by the company Seculo XXI on 11/29. Completion is expected for April/19.
Gesteira
On 31/10, a meeting was held with the Commission of the Affected Parties of Gesteira, AEDAS and Renova Foundation, in which the terms of the agreement were discussed and how to handle the 37 cases. It was agreed that the Renova Foundation should forward the planning (stages of environmental studies, water viability, etc.) to be compatible with the work plan being prepared by AEDAS and the Commission.
On 11/27, a meeting was held with the Gesteira Municipal Office to present the proposals that are still being validated by the community for the implementation of the resettlement and clarify the procedures that must be authorized by the Municipal Office for the implementation of the project.
Social Management
On 11/10, the first visit of the Commission of Affected Parties of Bento Rodrigues took place to monitor the resettlement works. Visitors inspected the works in conjunction with the implementation and Social Management areas, passing along the streets that can already be accessed, the demarcated blocks and three lots that went through the preliminary earthworks.
In the Housing/Interdisciplinary Working Group, held on 11/13, it was agreed that the Commissions of Affected Parties of Bento Rodrigues and Paracatu de Baixo will meet with the Renova Foundation, within 15 days, for presentation and definition of the companies that will perform the resettlement works, as well as contracting deadlines and criteria.
On 11/22, the activity “Cultural Solidarity Gathering” was held with the Seniors Group, in partnership with RECRIAVIDA.
Progress was made in discussions with the Community and Technical Advisory Body on New Households and Priority Process for choosing available land.
On 11/26, another purchase and sale agreement was signed for the acquisition of a property for family resettlement (assisted purchase) - serving 11 families. The cumulative total is 9 signed contracts, serving 11 families. Two contracts are for lots on which 2 buildings will be built (choice of those affected).

Bento Rodrigues
Filed, on 10/01, with the Municipal Office of Mariana, the consent received by SAAE for the detailed projects of the sewerage network and water distribution network of the Bento Rodrigues resettlement. The consent protocol was one of the conditions for the resettlement permit. The Plan for the Emergency Recovery of the Mariana Landfill was also filed with the Municipal Office of Mariana on 10/04. This project aims to recover the structures of the Mariana landfill to optimize its operation and to receive the waste of the resettlements.
On 10/04, a joint inspection was carried out of the works in the cafeteria and an agreement was reached on 10/26 to start the installation of the equipment by Sapore (company responsible for operating the cafeteria).
On 10/12, a party was held in the Bento Rodrigues resettlement in celebration of Children's Day. The party was attended by the entire affected community and featured recreational workshops, games and toys for children.
On 10/18, the plant suppression activities in area 1 were completed and, on 10/24, the plant suppression was completed in the access around wells 3 and 4 and in the WWTPs 1 and 2. This way, the physical progress made with the plant suppression activities reached 99%.
On 10/20, JM started transporting the surplus wood material to Santa Rita Durao (MG).
On 10/24, the consent by SAAE was received for the detailed projects of the wastewater treatment plants. On 10/25, the works to put into operation well 4 were completed, releasing it for water withdrawal. Both were conditions of the urban licensing for the Bento Rodrigues resettlement.
On 26/10, the first visit of architects and Social Management team took place in the new Bento Rodrigues development to see the lots and learn about the script used. This action served as a test to start the visits that will be made by affected people during the execution of the works.
The physical structure of the Support Center for the Affected People was opened to start its activities on the construction site of the Bento Rodrigues resettlement. This Center will be the support structure for carrying out visits to the lots and receiving affected people during the works.
Paracatu
On 10/01, work began on improving the access to the lots of Paracatu de Baixo (section of Furquim Street).
On 10/03, a Working Group was held with the Commission of Affected Parties from Paracatu de Baixo, G20, Technical Advisory Body and Renova Foundation, to present the proposed methodology for designing the houses and commercial properties with the families. On 10/10, the methodology for a pilot workshop was presented for designing the houses and commercial properties.
On 10/04, a workshop was held to rescue the cultural patrimony EPIC/RIPC (Preliminary Cultural Impact Study/Impact Report on Cultural Patrimony) with the Commission of Affected Parties of Paracatu de Baixo, G20, Technical Advisory Body and Renova Foundation.
On 10/19, kick-off of the company Seculo XXI, responsible for the execution of plant suppression and fencing of the Paracatu de Baixo resettlement area.
On 10/22, the acquisition was approved of the area needed to carry out works to improve the access to the Paracatu de Baixo resettlement.
The engineering projects for the environmental licensing process were completed. Filing for environmental licensing at the Secretariat of Environment is expected for November 2018.
Gesteira
On 10/16, a meeting was held with the community of Gesteira to discuss the proposal for the agreement of case studies for access to family resettlement. Scheduled for 10/31, a joint review between the Renova Foundation, Technical Advisory Body, Commission and Prosecution Service, regarding the terms of the agreement of the case studies for access to family resettlement.
Social Management
Approval of the conceptual projects of the first public facilities for the affected community of Bento Rodrigues: approved were the projects for the school, health center, service center, squares, parks and landscaping.
Approval of the conceptual project of the Paracatu de Baixo resettlement by the affected community: approved with 97% of the votes in favor.
Signing of the first purchase and sale contract for the acquisition of property for family resettlement (assisted purchase).

Bento Rodrigues
Completion of plant suppression at the provisional access road, giving way to initiation of earthworks to execute the deviation, aiming at minimizing traffic and allowing greater safety within the project.
Initiation, on September 4, of the earthworks activities in two shifts.
Continuity of plant suppression in areas 01 and 02, with priority being given to projects that cover the largest amount of lots and involve the most earthworks. Completion is expected towards the end of the second week of October.
Paracatu de Baixo
Begin September (09/04), the request for license exemption for installing the construction site was filed with the Environmental Department, the same procedure that was done for Bento Rodrigues.
The conceptual urban project of the Paracatu de Baixo resettlement was approved by the community in an Assembly held on 09/13.
Voted and approved in the Municipal Council, on 09/24, the 1st Bill that allows the creation of a special guidelines area (ADIES) for resettlement projects, necessary for Paracatu de Baixo.
On 09/26, we presented in the Working Group the licensing process for the resettlement of Paracatu de Baixo to the Commission of Affected Parties, G20 and Technical Advisory Body.
Gesteira
An letter was filed on 09/03 with the Prosecution Service for Foundations regarding the negotiation process for the acquisition of the Gesteira plot.
A draft of the Term of Commitment to include seven households in the collective resettlement of the community of Gesteira was forwarded to the Commission of Affected Parties on 12/09.
Infrastructure
Barra Longa
Completion of the landscaping of the demolished house of Mr. Antonio Luiz Goncalves (Riso);
Delivery of 2 reconstructed residences: Mr. Dirceu da Luz (RCEDI-0039);
Works started at tailings dump;
Mariana
Completion of Mr. Marcio de Souza’s Reconstruction;
Mobilization of the company to fill potholes (maintenance of paved roads) in Monsenhor;
Completion of 13 support structures (Gates, Cattle grids and water dispenser).
Access Roads
Conclusion of maintenance of unpaved roads - Ponte do Gama x Paracatu de Cima (Bus stop) - 8km and Paracatu de Cima Left Bank - 1.8km
Social Management
Approval of the conceptual projects for the first public facilities for the affected community of Bento Rodrigues: the projects for the school, health center, services center, squares, parks and landscaping were approved.
Approval of the conceptual project of the Paracatu de Baixo resettlement by the affected community: approved with 97% of the votes in favor.
Signing of the first purchase and sale contract for the acquisition of property for family resettlement (assisted purchase).

Bento

On August 1, 2007, the Municipality of Mariana issued the Urban Development Permit for the Bento Rodrigues Resettlement, which authorizes the Renova Foundation to start its works in the Lavoura area.
On 08/03, an ecumenical service was held to commemorate the initiation of the Bento resettlement works at the construction site in the Lavoura area, which was attended by the affected community, municipal government of Mariana, prosecutor’s office, churchgoers, Renova staff and contractors.

Held on 08/10, a meeting at the Town Hall of Mariana for validation of projects of public use. The meeting was attended by the deputy mayor and several representatives of secretariats who validated the projects and requested some modifications. Presented were the projects of the School, Service Center, Health Center, Sports Court, Soccer Field, Linear Park and Squares.

Held between August 20 and 25, conversation circles with those affected at the Convention Center of Mariana regarding the development of real estate projects for public use. Featured projects: School, Health Center, Service Center, Linear Park, Soccer Field, Squares, Sports Court, Water and Sewage System, Paving and Lighting.

On 8/21, were initiated the civil works of the Visitors Center. This structure will be part of the construction of the Bento Rodrigues resettlement and will be used to develop the work by the Social Management team and for receiving those affected during visits made to the site.

On 08/30, the following executive projects were filed with the Municipal Government of Mariana: Paving, Pluvial Drainage and Containment of the main access, in addition to the ART of the EIV (Neighborhood Impact Study). These deliveries were outlined in the Building Permit of the development and are conditions of the urban licensing.

Paracatu de Baixo

In the Interdisciplinary Working Group/Housing held on 08/01, the criteria for the inclusion of the rural farmers to the collective resettlement project of Paracatu de Baixo were defined, with only ten farmers formally included in the conceptual project.
An informative session was held on August 9, 10 and 11 on the conceptual urban project of the resettlement of Paracatu de Baixo, for the Community, Commission of Affected Parties and Technical Advisory Body (Caritas).

In order to improve the access of machinery and equipment to the Paracatu de Baixo resettlement and safety of the access road, on 8/15 a request was filed at the Secretariat of Works, COMPAT and Civil Defense, for a construction permit for works to improve the access to Furquim Street.

On 8/20, a visit was made, together with the technical resettlement implementation team and the Municipal Government of Mariana, to Paracatu de Baixo and to the host area of ​​the Paracatu de Baixo resettlement to get to know the area.

A Public Hearing took place on 8/22 to discuss the Bill to amend the Master Plan of Mariana/MG to enable the creation of special guidelines for resettlement projects, necessary for Paracatu de Baixo.

Rescheduled to 9/13, in a WG (Working Group) held on 8/29, the Assembly with the community of Paracatu de Baixo to vote on the conceptual resettlement project.

Since the works for setting up the Paracatu de Baixo construction site are expected to start in October/2018, a request to waive the environmental license for the Paracatu de Baixo construction site was filed on 04/09 with the Secretariat of Environment, expected to be released within 30 days. After the works are released by the Secretariat, which depends on the protocol scheduled for September 12, activities will be initiated only after the release by the Municipal Government of Mariana/MG.

An Informative Meeting was held with the community of Paracatu de Baixo, on 09/05, for presenting the conceptual urban project and agreements for the assembly to vote on the resettlement project, which is scheduled for 09/13.

Gesteira

On 08/03, an Assembly was held in the community, summoned by the Commission of Affected Parties with the presence of the MPF (Federal Prosecution Service) and SECIR (State Secretariat of Towns and Regional Integration) requesting answers regarding the eligibility case studies of 7 families for the collective resettlement of Gesteira.

The MPF sent a requisition to the Renova Foundation on August 5, requesting an answer regarding the case study families. A draft agreement is being prepared by the Renova Foundation on the 7 families that are part of the resettlement eligibility case study.

Filed, on 08/17, with the Commission of Affected Parties, are the preliminary environmental and topographic studies of the terrain for technical analysis of the area indicated for the resettlement of the community of Gesteira. Scheduled for February 2019 are the delivery of consolidated environmental studies.

Filed on 09/03, with the Prosecution Service for Foundations, is the letter to assess the acquisition process of the terrain indicated for the resettlement of the community of Gesteira. The Renova Foundation is awaiting a response from the Prosecution Service for Foundations to continue the negotiation process for acquisition of the terrain.

Social Management

Conversation circles for validation of the conceptual design of public facilities - school, health center, service centers (post office, police station, municipal guards and municipal service center), landscaping, squares and infrastructure (water treatment, sewage, public lighting, telephony and paving).

In total, 152 people participated in the circles, we received 245 positive calls, 121 calls about points that need our attention and 248 suggestions.
Assembly for approval scheduled for September 12.
5th Meeting with Families - Step: Understand the methodology for designing the houses.

Revision of the conceptual project of the resettlement considering the demands identified in the presentations of the project elaborated using PRD - Participatory Rapid Diagnosis.

Scheduled for September 13 is the assembly for approval (voting) of the conceptual project of the resettlement.

Handed over the keys of the first house that was rebuilt in the rural area of ​​Mariana. New deliveries are planned for the coming months.

Trip to the “Fish & Pay” in Santa Rita, Ouro Preto, with a Group of Elderly and Relatives. Twenty-one elderly and 17 companions participated.

Bento Rodrigues

Submitted by SEMAD, on 7/5, was the document formalizing the Environmental License for the main activity of Urban Land Allotment, authorizing its implementation and operation. The General Property Registry (RGI) was also received on behalf of the Renova Foundation.

On 7/12, construction works were completed of the temporary bridge to access the well to withdraw water from Novo Bento by the company SEMD and, on 7/16, the authorization was granted by the Renova Foundation for the management of Fauna (rescue/save/transport) in Bento Rodrigues, which allows the animals to be rescued in the area of Lavoura during the execution of the works.

The second phase of the Registration process of the affected parties started on July 20. This phase will inspect the registrations that were made in the 1st phase. Expected completion by October 2018.

On 07/20, the administrative office was inaugurated and the Bento Rodrigues Resettlement team was mobilized for the construction site in the Lavoura area and, on 7/27, a meeting was held with the Municipality of Mariana/Secretariat of Construction Works to carry out deliveries and pending alignments in relation to obtaining the building permit for the development.
Gesteira

The following studies were finalized: passive environmental analysis, flora and fauna, speleology, PPAs, agricultural aptitude and water availability.

The installation/configuration of the equipment of the computer room in the Barra Longa school was completed.
A request was put in for the acquisition of images of the host area of Gesteira to issue legal advice regarding the Legal Reserve.

Paracatu de Baixo

On 7/4, the Preliminary Consultation on the resettlement of Paracatu de Baixo was filed with the Municipal Government of Mariana to verify the feasibility of the allotment in accordance with the Municipal Master Plan. The Municipal Government will issue a technical opinion within 30 days.

The workshops for the design of the conceptual project of the resettlement together with the Community of Paracatu de Baixo was evaluated on 07/11.

On 07/24, new adjustments to the Conceptual project for the resettlement of Paracatu de Baixo were presented to the Community, Commission and Technical Advisory Body.

Published in the Official Gazette de Mariana (local newspaper), on 08/03 was the announcement of a public hearing, to be held on 8/22, at 7:00 pm, to discuss the Bill (PL) to amend the Master Plan to enable the creation of an area of special guidelines for resettlement projects.

Social Management

The 3rd and 4th Meeting with Families - Phase: Learn about the methodology for designing the houses. This phase involves a group of families, the architects who will develop the project, social area and Technical Advisory Body. After this phase, the next step is to draw up the design individually with each family.

Presentation and validation of the methodology for the hearing related to public facilities. It was necessary to establish a methodology for project design and validation in a participatory way.

Review of the criteria for the insertion of rural farmers who will go to the collective resettlement. As requested by the Commission and agreed with the community and Technical Advisory Body.

The construction of the conceptual resettlement project was finalized, contemplating the Participatory Rapid Diagnosis - DRP.

There were also trips to the fish & pay pond in Santa Rita, Ouro Preto, with elderly and families. During the pre-housing process, monthly events are held with the community.
Engineering

Documentation for infrastructure and external power supply packages in Gesteira was completed on July 1.

The final documentation was submitted to the SEMAD on 07/05, supplementing the issuance of the Environmental License for the implementation of the Bento Rodrigues Resettlement.

Prior issuance, from 07/26 to 07/06, of purchase documentation (Technical Requisitions, PQ, CDM) of the school, health care unit, and service points of Bento Rodrigues, to meet the needs of the implantation.

On 07/12 the Paracatu urban planning project was presented to the Commission and the resettlement project was prepared for validation, with the participation of the Engineering team and together with the Dialogue Team.

Delivery of the final scale model of Bento Rodrigues. The scale model will be displayed at the construction site of Bento Rodrigues. Awaiting the construction of the Visitors Center for its delivery.

Upcoming deliveries
● Preparation of the documentation for the clover package for access to Bento Rodrigues.

● Delivery of the project for the electric distribution network of Bento Rodrigues.

● Preparation of documentation for the contracting package for the Bento Rodrigues Sanitary Landfill works.

● Presentation and validation of the conceptual project for the public facilities of the Bento Rodrigues resettlement at COMAR and with the Community - Round Table Conversation with the Community.

● Planning of agenda in the WG of Paracatu for presentation of the licensing process

● Validation of the conceptual resettlement project of Paracatu de Baixo with Community.

● Creation of spaces for continuous training of the teams.

● Protection of the archaeological site before initiation of the works in Rua Furquim.

● Elaboration of Productive Backyard Plan for families.

● Completion of policies, procedures and flows of tickets, aimed at transparency and agility.
Challenges

● To consolidate, together with the public authorities and the Residents' Commission, a plan for the recovery of the deadline for the environmental and urban licensing schedule of Bento Rodrigues.

● To consolidate, together with the Community, the Paracatu de Baixo urban project, in view of the recommendations of SECIR and SEMAD.

● To consolidate the polygonal area to be acquired for the resettlement of Gesteira together with to the community, the Technical Advisory Body and the owner of the land.

Bento Rodrigues

The Board of Councilors approved, in a single vote, Bill 3,220, which authorizes the donation of nine pieces of land to the Renova Foundation, for the resettlement in New Bento. The approval took place on June 11 and the project was signed by the Mayor of Mariana on June 12.

On the 18th, the revision of the urban project of Bento Rodrigues was filed with the State Secretariat for Towns and Regional Integration (Secir) and the Municipal Government.

Whereas on the 21st, at Mariana's Notary's Office, the deed of donation of the parcel of Lavoura land was signed.

On June 25, the Technical Board for the Protection of Biodiversity and Protected Areas approved the proposal to compensate for the suppression of Atlantic Forest for the Bento resettlement. On that same day, a work order was issued to initiate the mobilization of the resources needed to carry out the vegetation suppression activities in the Lavoura area.
The activities will be executed after the issuance of the environmental license and building permit.

Gesteira

The land owner Mauricio Gomes released, on June 13, the host area of ​​Gesteira. Thus, environmental studies (flora, fauna, water availability, agricultural aptitude, speleology, etc.) and engineering studies (topography, planimetric and altimetric survey, water studies, among others) were released.

On that same date, a visit was made to this possible host area for the resettlement. The action was attended by the Commission of Affected Parties of Barra Longa, community of Gesteira, technical advisory body (AEDAS) and the Renova Foundation.

The objective was to promote the physical recognition of the land indicated by the community, to observe the physical and natural characteristics of the area.

Whereas on the 25th, a case study was completed to define the eligibility of families for collective resettlement of the community. The nine pending cases of the in total 37 eligible families were completed. The result of these latest case studies will be made available by the Renova Foundation for analysis by the technical advisory body of the esteira
community (AEDAS).

Paracatu de Baixo

On June 14, the RGI (General Registration of Property) was issued for two of the parcels of land of New Paracatu de Baixo on behalf of the Renova Foundation. With this, two parcels remain to be registered, which have pending inventory. The next steps are the registration of inventories and “bonis non administratis” in the RGI Registry and the of the
registration of real estate on behalf of the Foundation.

On June 30, the participatory workshops for the conceptual design of the Paracatu de Baixo resettlement were finalized. This initiative was divided into four stages of joint construction, together with the community of Paracatu de Baixo, Technical Advisory Body (Caritas) and the Renova Foundation.

The next steps of this work are the evaluation of the workshops with the community, adjustments made by engineering (according to the Rapid Participatory
Diagnosis (DRP) elaborated during this activity) and the presentation of the final project.

Furthermore, the preliminary consultation of the resettlement of Paracatu de Baixo was filed with the Municipal Government of Mariana to verify the feasibility of the subdivision in accordance with the Municipal Master Plan. The Municipal Government will issue a technical opinion within 30 days.

Social Management

The following activities were carried out:

● Listening to families who fit into resettlement case studies. Feedback to the community, Commission and Technical Advisory Body for July;
● Completion of two stages of the resettlement process of Bento Rodrigues: visit to the host area with the commission, technical advisory body and community to design the resettlement of Bento and construction of the resettlement project with those
involved;
● Housing working group;
● Validation of the term of use and responsibilities of the vertical garden in the community garden;
● June Celebration in partnership with Recriavida, with the participation of 25 elderly people and 38 companions;
● Definition of requirements (collective equipment) for the construction of the main office of the Bento Rodrigues Residents Association, Linear Park and CRAS, as well as the School, squares, gymnasium and soccer field;
● Visit with residents to Bento, for on-site verification of collective equipment still existing in the community (Church of Merces, Evangelical Church, Residents' Association, Gym and Bento Rodrigues Farmer’s Market Association). The methodology for designing houses and collective equipment was also defined;
● Definition of the requirements for construction of the spaces for the Town Clerks
Office, Municipal Guard, Post Office and Point of Support for Military Police;
● Completion of the stage “Meet with Architects” for the 2nd Group of Families, totaling 25 households.

Engineering

The team visited the host area of ​​Gesteira with the community, Commission of Affected Parties, Technical Advisory Body (AEDAS) and Renova Foundation. The owner of the host area also allowed initiation of the engineering studies.

In order to obtain the Installation License (LI) and a permit to start the works, a revision of the Bento Rodrigues urban project was filed with Secir and the Municipal Government of Mariana. In addition, the deed of donation of the land where the village will be built was issued by the Municipality of Mariana to the Renova Foundation.

The workshops with the community to design the conceptual project were also finalized and its approval is scheduled for July. It will supplement the development of the Paracatu de Baixo urban development project.

Bento Rodrigues
On May 15, the Municipality of Mariana issued a declaration of compliance to the Environmental Licensing procedure filed with the Priority Projects Office (Supri). As early as May 16, the Municipal Government had issued a term authorizing the start of the enterprise in the Lavoura site.

In that period, amicable expropriation deeds for the Lavoura site were also signed by the company Arcelor, the Mariana Municipal Government and Renova. The General Property Registry (RGI) was also issued on behalf of the Renova Foundation. On May 21, Incra also issued a document characterizing the use of soil in the Lavoura site as urban, and no longer rural. On May 22, the RGI for the Lavoura site was issued on behalf of the Municipality of Mariana. The vote on the Donation Bill is scheduled for June.

In addition, the contract with the company SEMD Caldeiraria came into effect in this period. The company is now in charge of building a mixed bridge (made of concrete, with a metal structure) in Bento Rodrigues. The bridge will be used to access the water well and the project’s Sewage Treatment Plant.

On May 23, the environmental studies of Bento Rodrigues were officiated at Semad, formalizing the environmental licensing process. On May 29, the J+T architects started interviewing the affected population of Bento Rodrigues to design the house projects. These projects will be developed alongside the families, in order to meet all the desires of those involved. This work is expected to be finished alongside each resident in 45 days.

Paracatu de Baixo
Residents of the community and representatives from the Technical Advisory Body (Caritas) evaluated and validated the methodology pilot for conceiving the Paracatu de Baixo resettlement project. The project was signed off on during a Working Group meeting held on May 3. On May 8, during another Working Group session, the methodology schedule for this project’s conception was drafted. The community, the Paracatu de Baixo Commission of Affected Parties and the Technical Advisory Body all took part in this project. Another community-oriented initiative were the participatory workshops to design the resettlement project, an activity in which Caritas and the Renova Foundation also participated. On May 24, the second stage of these workshops was also finished. During the activity, the community became acquainted with the resettlement area using maps and a scale model of the host area, which were based on the original area map.

There were also 16 new registrations for the Paracatu de Baixo site on behalf of the Renova Foundation at the Mariana RGI. Thus, there remain two registrations, which have pending inventory payments and registered under the Foundation’s name.

On May 22, the 4th Interdisciplinary/Housing Work Group meeting took place at the Mariana Convention Center. The meeting was attended by representatives of Samarco, Vale, BHP Billiton, the Renova Foundation, the Mariana Commission of Affected Parties, SECIR, SEMAD, the Mariana Municipal Government and the communities of Bento Rodrigues and Paracatu de Baixo. As per the planned schedule, the Renova Foundation presented conclusive studies on water availability and sanitary issues in Paracatu de Baixo.

Gesteira
On April 11, a Working Group session was held to define the eligibility criteria for resettlement. Participants in the meeting also authorized the Renova Foundation to proceed with the acquisition process for the 40-hectare tract land, as suggested by AEDAS.

The Interdisciplinary/Housing Work Group was also established, with bi-weekly meetings. The affected community and their commissions, PMG, Technical Advisory Body (Caritas), Renova, SEMAD and SECIR, the Municipality and CODEMA now all participate in this Forum. This way, Bento and Paracatu de Baixo Working Groups will be joined, and the Gesteira community will participate as listeners.

The first meeting in this structure took place on April 25. During the meeting, a unified methodology proposal for a family resettlement, presented by the Renova Foundation, Caritas and the Commission of Affected Parties, was discussed.

On May 7, the affected parties and Technical Advisory Body (AEDAS) and Renova Foundation representatives 13 more names for the Gesteira resettlement, totaling 18 names eligible for resettlement.

On April 9, a meeting was held to mark the kick-off of the activities by the Cerne company, responsible for project preparation, documentation and preparation of panels for setting up the construction site of Novo Bento. On that same day, the certificate of the location of the village was signed at the National Institute of Settlements and Agrarian Reform.

A unified proposal for the methodology for family resettlement was defined in a Working Group that includes the Renova Foundation, Caritas and the Commission of Affected Parties.

Throughout this month, there were discussions related to the mobilization of staff, equipment and machinery - to enable the effective start of activities at the construction site.

The Technical Advisory Body also validated the methodology for discussing the Paracatu de Baixo urban development project. Sixteen Real Estate Transfer Tax (ITBI) payments have already been paid by the Renova Foundation, meaning there are only two pending left, due to inventory issues.

The eligibility criteria for the resettlement of Gesteira were defined, as well as the alterations to the polygonal area of the project to be implemented. The Renova Foundation will proceed with the acquisition of 39.2 hectares of land, as suggested by the State Environmental and Social Defense Association (AEDAS).

An Informative General Assembly was held on March 21 with the community of Bento Rodrigues (MG), to provide clarification on the progress of the resettlement activities after the approval of the urban project, and the next steps (licensing, land registration, works, deadlines).

In a hearing in the Court of Mariana, part of the guidelines for the resettlement process of Bento Rodrigues, Paracatu de Baixo and the reconstruction of other affected rural communities was validated. The guidelines were approved by the Prosecution Service of the State of Minas Gerais (MPMG).

The Renova Foundation completed the payment of the Real Estate Transfer Tax (ITBI) for 80% of the land in the Paracatu de Baixo (MG) community, totaling 392 hectares. End March, the negotiation with the Commission of Affected Parties and Caritas (technical advisory body) to define the methodology for discussing the conceptual urban project was finalized. As with the community of Bento Rodrigues, the objective is for the housing and public areas of Paracatu de Baixo to meet the needs of future residents, preserving their habits, neighborhood relations, and cultural and religious traditions.
In Gesteira (MG), the Commission of Affected Parties, together with the technical advisory body State Environmental and Social Defense Association (Aedas), presented its proposal for the measurements of the resettlement of the village. Until then, based on conversations with the group, the resettlement was defined for 20 families. In the new proposal, the association claims the resettlement of 37 families and defined a minimum area of 5 thousand square meters per family. The proportion the commission is requesting for each family is five times higher than they had in the old village. The lap of land desired by the commission totals 39 hectares. Previous planning foresaw 6 hectares.

An important step was made with the approval of the Bento Rodrigues Urban Project by the community in an Assembly on February 8, in Mariana (MG). Another important fact that occurred concerns the initiation of the registration process for those impacted from Bento Rodrigues and Paracatu de Baixo, in Minas Gerais.

Participation in the Public Civil Action of conciliation in Mariana (MG) occurred on 02/02 to define the guidelines of the Resettlement Support Plan, filed on 02/06 in Mariana (MG).

The proposal of the polygon in Gesteira (MG) was presented on February 24 by AEDAS and the commission of affected parties of Barra Longa to the Renova Foundation, with the participation of the Federal Prosecution Service.

Complementary environmental studies (agricultural aptitude and water availability) were filed with the Technical Board to corroborate the fertility of the Gesteira (MG) territory.

After the consolidation of the urban project, a result of the workshops with the community of Bento Rodrigues, and agreed with the Commission of Affected Parties, Prosecution Service and maintainers, the assembly for validation of the conceptual urban project was scheduled for January 27. On January 25, as advised by the Prosecution Service of Minas Gerais (District Attorney's Office of the Mariana District), the Commission of Affected Parties requested the cancellation of the meeting, even with all agreements signed and in compliance. On that occasion, the Commission requested that the meeting be held after the conciliation hearing, which will deal with the enforcement action proposed by the MPMG to the maintainers, scheduled for February 6. Out of respect for the decision of the Bento Rodrigues Commission of Affected Parties, the Renova Foundation canceled the meeting on the date in question.

Other steps still need to be completed, such as the approval of the final version of the conceptual urban project by the Bento Rodrigues community and the expropriation of the land by the Municipal Government to regularize the General Property Registry (RGI) on behalf of the Renova Foundation, process that depends on the approval of the project by the community. 225 families will be resettled.

With regard to the resettlement of Paracatu de Baixo (MG), the last two lots that make up the host area were acquired in January and all public deeds of purchase and sale were drawn up. The next step is the regularization of real estate on behalf of the Renova Foundation with the RGI.

The State Department of Towns and Regional Integration (Secir) and the State Department of Environment and Development (Semad) issued a technical report with recommendations for the development of the urban development project of Paracatu de Baixo. In order to comply with the recommendations, the Renova Foundation carried out new complementary environmental studies, prepared a technical report and forwarded it to the respective bodies and to the Municipal Commission for Matters related to the Renova Foundation (COMAR) of the Municipal Government of Mariana and the Commission of Affected Parties of Paracatu de Baixo.

In Gesteira (MG), negotiations are underway with the owner for the acquisition of the polygonal (host) area. During this period, the State Environmental and Social Defense Association (AEDAS), the technical advisory body of the community of Gesteira, is developing a conceptual urban project with the community for discussion and validation with the Renova Foundation.
Planned, for those families whose houses cannot be rebuilt in their original areas (rural areas) and families that refuse collective resettlement, is the option to acquire a new property (via assisted purchase), considering the same characteristics and constructive property equivalent to that prior to the dam collapse, in a place to be chosen by them.

Following the criteria and guidelines of the Resettlement Assistance Policy, assistance started for three affected families of rural communities, in the form of Assisted Purchase, a commitment signed in the minutes of the meeting held on December 21, with participants from rural communities, including committees, Caritas, Movement of Those Affected by the Dam (MAB), Renova Foundation and its third parties Synergia and H&P.

The Renova Foundation also carried out the transition of the social accompaniment actions to the company Synergia, which took over the collective thematic activity of the group of elderly and family members, the monitoring of the group of the Colina community garden and the individual accompaniment of the impacted families, residents in temporary rented housing, in Mariana.

In this transition period, in order to provide a satisfactory environment for the groups and families involved in the actions, the teams of the Reconstruction of Villages Program and Synergia worked together developing the following actions: home visits with the elderly to present the Synergia social team and mobilization for the masks workshop; visit to members of the Community Garden; and the realization of the Mascaras workshop, a complementary activity that precedes the participation of the elderly group in the carnival event in RecriaVida, scheduled for the beginning of February.

Regarding the socio-cultural actions, the Renova Foundation followed the three kings parade of Paracatu (MG) and held meetings with the group of religious and young people from Gesteira (MG) to evaluate the feast of Our Lady of Conception patroness, held in December 2017, and define the next activity of the youth group: 1st Fishing Championship.

Also, in the community of Barreto (MG), an action was started to support the Three Kings event in the community. Subsequently, data was collected for the preparation of the annual, monthly and weekly calendars of community celebrations and events.

The Bill that modifies the Master Plan of Mariana (MG) was approved and sanctioned so that part of the land of Lavoura, that will house the new town of Bento Rodrigues, can be used for urban expansion. The modification of the site was a legal prerequisite for land use and occupation, and the thereafter division of land into lots. It is a major milestone, paving way for the other resettlement processes to be initiated, such as the issuance of the construction permit and environmental licensing.

Other steps still need to be overcome, such as the expropriation of the land by the Municipal Government to regularize the General Property Registry (RGI) on behalf of the Renova Foundation, which is already underway, and approval of the final version of the conceptual urban project by the community of Bento Rodrigues. 225 families will be resettled.

In the case of the urban project, the process is being constructed together with the communities. The principle is that the dwellings and public areas of Bento Rodrigues and the other villages that will be built will meet the needs as raised by future residents, preserving their habits, neighborhood relations, ways of life and cultural and religious traditions.

Regarding the resettlement of Paracatu de Baixo, the State Department of Regional Towns and Integration (Secir) and the Secretary of Environment and Development (Semad) issued a technical report with recommendations for the development of the urban development project. The completion of the acquisition of the sites depends on the regularization of the documentation of one lot, which is being done by the owners.

In Gesteira (MG), negotiations are underway with the owner for the acquisition of the polygonal host area. Its conclusion depends on the validation of the area by the Residents Committee.

As part of the process for social support to the families, the Renova Foundation, through the Resettlement and Social Protection programs, carried out an action to integrate and support the social assistance services of the municipality of Mariana (MG) with the objective of strengthening the partnership for the development of joint actions.
The initiative provided the group of elderly with information on the public equipment and moments of interaction with the other residents of Mariana during the participation in the end-of-year fraternization event at RecriaVida.

Renova supported and participated in the novena (nine days of prayer) and the feast of Our Lady of Conception, patroness of the community of Gesteira (MG). In the same way, it supported the Three King’s Day parade of Paracatu, the two Three King’s Day parades of the community of Barreto and the recital of Christmas, presented by the youth group of Bento Rodrigues in the nursing home of Mariana. Structured actions regarding the local cultural identity were also started in Barreto.

Workshops were held with the community to evaluate the scale models of the two alternatives for the new village of Bento Rodrigues (MG). In all, 23 workshops were held with a total of 499 participants (representing 164 families). The observations and comments collected will be consolidated in a unique urban development project, which will be validated by the community in a meeting.

A public hearing was also held for discussing the Municipal Urbanization Law Project of the area where the village will be rebuilt. The comments are being evaluated by the Municipal Government and a new hearing will be scheduled for approval of the law by the Municipal Council, approval and publication by the Municipal Government.

The regularization process of the acquired land proceeds its phase of consolidation of the decree of friendly expropriation by the Prosecutor of the Municipal Government of Mariana.

Regarding the resettlement of Paracatu de Baixo, the State Department of Regional Towns and Integration (Secir) and the State Department for Environment and Development (SEMAD) issued a technical report with recommendations for the development of the urban development project. The completion of the acquisition of the sites depends on the regularization of the documentation of the two lots, which is being done by the owners with the support of the Renova Foundation team responsible for land regularization.

The commission of affected parties and the community of Gesteira were presented the area that the owner of the chosen site is willing to sell, but it was not accepted. The negotiation to acquire the area from the owner has started, but its conclusion depends on the approval of the commission of affected parties. The technical advisory body of the affected parties is carrying out a study on the chosen site, to evaluate its approval.

As part of the social family support process, which focuses safeguarding the social identity and affective memory of the elderly and their families, a gathering was organized at the Casa dos Saberes in Mariana (MG) for an afternoon dance with typical foods. Also during this period, Renova validated the Regulation of Use and Responsibilities of the Community Garden of Colina with the members of the community garden. In addition, it helped with the planning of the feast of the patroness of Gesteira, scheduled for the beginning of December 2017. The musical events, with groups from the communities of Bento Rodrigues, Paracatu and Gesteira, took place during this period according to a joint agenda with the community, the instruments and methods being used: guitar, percussion and choral singing.

The preparation of the Municipal Urbanization Bill Project was completed in the area where the new village of Bento Rodrigues will be built, so that the area, now rural, is transformed into an area of urban expansion. This project will be presented at a public hearing to be then forwarded to the Municipal Board and then sanctioned by the Municipal Government. The approved bill will make it possible to open the process of the urban licensing process with the Secretary of State of Regional Towns and Integration (Secir).

For the Bento Rodrigues urban project, the scale models were created of the two alternatives for occupancy of the area, which will be presented at workshops in the community to gather the impressions that will help consolidate one single project.

The teams of the Secretary of State of Towns and Regional Integration (Secir) and the Secretary of Environment and Development (Semad) went to the country to visit the area where Paracatu de Baixo will be rebuilt. The environmental studies and the urban project, discussed with the community, were also sent to the organs for preliminary evaluation. A meeting will be scheduled for the collective construction of the environmental and urban licensing timeframes with the participation of Secir, Semad, Municipal Government and Residents Committee.

In a meeting with the owner of the area where Gesteira will be rebuilt, the polygon of the area to be acquired was consolidated. In November, the negotiation will begin to acquire it from the owner.

As part of the social family support process, the elderly and their families visited the Lavras Novas district in Ouro Preto (MG). In this period, Renova delivered a community garden for families in the communities of Bento Rodrigues and Paracatu. In addition, gatherings and musical workshops were held in the community of Gesteira and Paracatu. Support for the celebration of popular festivals also continued, especially the Celebration of Our Lady of Aparecida and the commemoration of Children's Day in the communities of Bento Rodrigues and Paracatu.

A working meeting was held between the Renova Foundation, the Secretariats of State of Towns and Regional Integration (Secir), the State Secretariat for Environment and Development (SEMAD), the Municipal Government of Mariana and the Residents Committee of Bento Rodrigues, for the process of environmental and urbanistic licensing for the reconstruction of Bento Rodrigues (MG). It was established that Renova will present, through scale models, two layout alternatives for the area to consolidate, together with the community, a single urban project that will be validated in assembly. The urbanization process (change from rural to urban area) will be carried out in parallel to the consolidation of the urban project.

In Paracatu de Baixo (MG), the signing of the last land acquisition contracts is awaiting a regularization on the owners’ end. Regarding the urban project, the Residents Committee has resumed evaluation, and the project is being adapted according to the comments made.

In Gesteira (MG), the negotiation for the acquisition of the host area is being carried out with the owner in conjunction with the negotiation of his indemnification (PIM).

As part of the social family support process, visits were made with the elderly and family to the Music museum and Sacred Arts museums in Mariana. In addition, a choir, singing popular songs, was created involving all the communities. During this period, Renova continued to support the celebration of popular festivals, especially the Baby Jesus Celebration and Folia de Reis, by the community of Paracatu (MG), and the Sao Vicente de Paulo Celebration, by the community of Gesteira (MG).

The Bento Rodrigues (MG) project was adjusted as requested by the Secretariats of State of Towns and Regional Integration (Secir) and Environment and Development (Semad), preserving as much as possible the original relationship between the town’s neighborhoods. The project continues to be evaluated by public agencies and the community. Parallel to the approval, the Urban and Environmental Licensing process and the Urbanization Law Project process (alteration of rural to urban area) are underway and so is the basic project required for the resumption of the hiring process of the infrastructure service.

In Paracatu de Baixo (MG), of the nine pieces of land that are in the process of acquisition, seven contracts have been signed. The two remaining are in the final phase of signing. Meanwhile, the Paracatu de Baixo urban project was revised to meet the guidelines of public agencies regarding the natural terrain slope and was referred to the Residents Committee for evaluation.

In Gesteira (MG), the Technical Advisory Body of the State Environmental and Social Defense Association (Aedas) was mobilized and the negotiation for the acquisition of the area chosen by the community was reopened.

Among the social support actions carried out with the families living in temporary housing, the following should be highlighted: the Vale Train ride on the Mariana-Ouro Preto route with elderly people and their families; the visit to the vegetable garden of Mr. Valdir Polak, in the community of Paracatu; the monitoring of the infrastructure work on the Community Garden Project in Mariana (MG); the mobilization of the Folia de Reis de Paracatu (MG) group and the musical event with the community of Paracatu

The Bento Rodrigues (MG) project was evaluated by the Technical Board of Infrastructure and by the State Secretariat of Urban Infrastructure and Towns (SECIR), which requested adjustments. The completion of the contracting processes for plant suppression and infrastructure of Bento Rodrigues will await the review of the project.

The report of the diagnosis of the Sanitary Landfill of the municipality was submitted to the Municipality of Mariana, in Minas Gerais.

In Paracatu de Baixo (MG), the negotiations with the owners of the other lands that must be acquired for the reconstruction of the village have progressed and are in the final phase. The urban plan of Paracatu de Baixo will be revised, taking into account the same comments made in the Bento Rodrigues project.

Social monitoring continues with several actions of integration of the families of Bento Rodrigues and Paracatu de Baixo, aiming to maintain the ties between them. Worth mentioning is the meeting with the elderly and family members at the Casa de Cultura, in Mariana (MG), for the “Musical Café" workshop. In Gesteira (MG), Renova supported the planning and participation in the event "Gesteira Aiá", a cultural festival of the community.

A meeting was held between public authorities, the Renova Foundation and the Residents Committee for a better understanding of the actions required to start the process for the Environmental Licensing for Bento Rodrigues (MG), together with the State Department for the Environment (SEMAD). At the meeting, task force groups were created that will define and monitor the implementation of actions. Parallel to the licensing process of Bento Rodrigues, the contracting of plant suppression and infrastructure services is underway.

In Paracatu de Baixo (MG), negotiations have begun with the owners of the additional lands that should be acquired for the reconstruction of the village. Meanwhile, the urban plan is being evaluated by the Residents Committee and Caritas.

In Gesteira (MG), the Technical Advisory Body of the State Environmental and Social Defense Association (AEDAS) is in the process of mobilizing support from the residents in the evaluation of the urban project of the new village.

Social follow-up actions continue to be carried out with the residents of Bento Rodrigues and Paracatu de Baixo, with emphasis on conducting conversations with seniors and students to answer questions about the resettlement.

In Paracatu de Baixo (MG), the contracts were signed for the acquisition of the first plots of land for the resettlement. The urban plan is being adapted, according to the comments made by the Residents Committee and the Technical Advisory Body (Cáritas).

Signed an agreement with the State Environmental and Social Defense Association (Aedas), which will provide technical advice to those that were impacted in Barra Longa (MG) and will work together with the technical team of the Renova Foundation to consolidate the urban project for the resettlement of Gesteira.

A group of 157 people from Bento Rodrigues (MG) visited Lavoura, site of the reconstruction, to be informed about the location of the main streets, the church and the school. Interested infrastructure services providers also visited the site, with the objective of collecting information for the preparation of technical and commercial proposals.

Alternatives and possibilities for water treatment and distribution in the Bento and Paracatu resettlements were discussed at a technical meeting, held in Mariana.

Participating in the event were representatives from the concessionaire Autonomous Water Sanitation Service (SAAE), the town council, the technical team of the Renova Foundation and Caritas.
Whereas, Cavo, a sanitation company contracted by the Foundation, presented the preliminary results of the diagnosis on the Sanitary Landfill of Mariana. The area allocated for the resettlement of Bento Rodrigues is about 2 km from this landfill, so this analysis seeks to identify possible impacts and suggest measures to revert them.

Soil studies were also contracted to survey the characteristics of Lavoura, necessary for the infrastructure projects of the Bento development, such as earthworks, containment, drainage, water and sewage network, etc.

In Bento Rodrigues (MG), environmental field studies were completed and the basic infrastructure projects were finalized, which will allow the initiation of the Environmental Licensing process and the contracting of infrastructure services. The contracting of the architectural project of the houses and equipment of collective use is in progress.
In Paracatu de Baixo (MG), the negotiation stage for the acquisition of the land was completed. The consolidation of the Urban Plan with the Residents Committee is in progress.
In Gesteira (MG), negotiations are ongoing for the acquisition of the land chosen by the community, with mediation of the Prosecution Service.
Initiated the round table conversations with groups of elderly people from Bento Rodrigues and Paracatu de Baixo to convey information about resettlement and integration activities (trips, songs, etc.).

In Bento Rodrigues (MG), the urban plan of the district was consolidated by the Residents Committee and Technical Advisory Body and the first survey campaign in the field of fauna, flora and speleology (science that studies or explores natural soil cavities such as caves and grottos) in the cultivation area. Whereas in Paracatu de Baixo (MG) the forest inventory work was completed for the first properties and the survey of the rural farmers for resettlement was also completed. Further ongoing in the district is the forest inventory work of the five new areas incorporated into the reconstruction project.

Ongoing are the studies of environmental impact on the sites chosen for the resettlement of Bento Rodrigues and Paracatu de Baixo (MG), as well as the identification and diagnosis of rural residents for resettlement, together with the Paracatu de Baixo community.

The urbanization project of Bento Rodrigues (MG) has been approved in accordance with the community and the basic projects are already in progress. In Paracatu de Baixo (MG), the geological studies were completed and the preliminary urban design was presented to the Residents Committee. Also ongoing is the negotiation process for the acquisition of land in Gesteira (MG).

Together with the community the validation process of the urban design of Bento Rodrigues (MG) was started, in addition to meeting with local authorities and Caritas Brazil to discuss the matter. Whereas in Paracatu de Baixo (MG), the validation of the expectations survey took place for the preparation of the Urban Design Concept, with the presence of 70% of households eligible for resettlement. A meeting was held with the State Department of Environment and Sustainable Development (Semad) to address the licensing strategies for the resettlement of the communities. Furthermore, in progress are the basic projects of the water and sewage systems, the construction sites and new accesses, both for Bento Rodrigues (MG) and Paracatu de Baixo (MG).

The urban design project of Bento Rodrigues (MG) was completed together with the residents' committee. In progress are the environmental impact studies of the Bento Rodrigues site and completed are the topography and survey of the land chosen for resettlement of the Paracatu de Baixo (MG) community.

Together with the community of Paracatu de Baixo, a survey was carried out about the expectations for housing and the village, as well as the beginning of the urban development project and studies regarding the analysis of topography and the exploration of the land destined for resettlement. In Bento Rodrigues, there are ongoing studies about the environmental impact on the land destined for the resettlement of the community. The construction of the school in Gesteira is in its final phase and will be delivered to the community in December.

The urban project of Gesteira has been completed, so are the survey, topography (geology in progress) and video for validating the urban project by the Bento Rodrigues community, as well as the voting for choosing the area for relocating Paracatu de Baixo. The installation of pre-molded concrete PVC and slab walls at the Gesteira School has been completed.


Share:

News about the program

Access here all the news related to this Renova Foundation program.

Reports

Access here the documents and reports related to this Renova Foundation program.

Leave your comment